Stan Thompson

Click Here to download a 1' X 4' Poster file

Element Trainer

Home Search Contents Periodic Tables

Up

 


Click here to learn more about this remarkable scientist.
Stan Thompson

Uranium Fuel ] Breeding Pile ] Bad Shit ] [ SGT's Facilities ] SGT's Process ] Michele Gerber ]

Thompson's Facilities

From: PLUTONIUM PRODUCTION STORY AT THE HANFORD SITE: 
PROCESSES AND FACILITIES HISTORY (Document Number WHC-MR-0521 )
by Michele Gerber, Ph.D. and is available to download
Thumbnail images  have been added to Gerber's text by the Webmaster. Click on the thumbnail for a full sized image.

4.0  RADIOCHEMICAL SEPARATIONS PROCESSING

                                                             AT THE HANFORD SITE

4.1  THE BISMUTH-PHOSPHATE PROCESS

4.1.1  Start-up of Radiochemical Processing at HEW

wpe1.gif (1474194 bytes)

          The earliest radiochemical processing operations at the Hanford Engineer Works using "hot" (irradiated uranium) feed began at the 221-T Cell Building, also known as T-Plant or T-Canyon, on December 26, 1944.  This event was historic because T-Plant was the first full-size radiochemical processing plant in the world.  The only previous radiochemical processing of irradiated uranium fuel elements had been done on an experimental scale at a facility known as the Clinton Semi-Works (or SMX), located at the Clinton Engineer Works in Oak Ridge, TN.[lxxxv]

4.1.2  T, B, and U Process Groups  

facili1.gif (124869 bytes)

          The original separations process used at HEW was the bismuth-phosphate (BiPO4) process.  It was based on the principle that bismuth phosphate is similar in crystal structure to plutonium phosphate.  The entire operation was a batch, precipitation process that achieved separation by varying the valent state of plutonium 239 (Pu-239), and then by repeatedly dissolving and centrifuging plutonium-bearing solutions.  The steps of the bismuth-phosphate process were carried out first in T‑Plant, then in the 224-T Bulk Reduction Building, and then in the 231-Z Isolation Building.  A second and third set of facilities for both the first and second phases of the BiPO4 process also were built at HEW, but the final steps always took place in the 231-Z Building.  The second set of facilities was known as the B Process Group, and consisted of the 221-B (B-Plant) and 224‑B Buildings and their associated support structures.  B-Plant began processing irradiated U at Hanford on April 13, 1945.  The third set of facilities was known as the U Process Group, and consisted of the 221-I (U-Plant) and 224-U Buildings and their associated support facilities.  The U Process Group never handled irradiated uranium, but served as a training facility until another use for the buildings was developed in 1952.[lxxxvi]

4.1.3  Original Separations Buildings  

          The 221-T Cell Building originally was 85 feet (25.91 meters) wide by 875.5 feet (266.85 meters) long by 102 feet high.  It was a dense, thick, reinforced concrete, rectangular mass, approximately one-quarter below grade, with no windows.  At the time that T-Plant was built, its design and construction was described by the DuPont Corporation builders as "extremely unusual...due to process requirements.  In other words, once the equipment in any of the cells is placed in operation, it will not be possible to approach it for maintenance or to manually remove or fit up piping."  Remote operational requirements, as well as radiation shielding requirements, resulted in the 221‑T Building being unique, and a first-of-a-kind structure in the world, when it was built.  The 221‑B Building was virtually identical to T-Plant, except that it had 65 feet (19.81 meters) less length and did not contain a special head-end testing laboratory that was included in T‑Plant.

hanford221u_figure2.jpg (124215 bytes) Good Match for 221-U Fig 2 of 221-T.jpg (279652 bytes) 221-T Canyon Below Grade Construction.jpg (311691 bytes)

          The foundation of each canyon building structure was a reinforced concrete pad varying from six to eight feet (1.83 to 2.44 meters) in thickness with a spread footing.  Outside building walls were likewise reinforced concrete three to five feet (0.91 to 1.52 meters) thick.  The barricade wall between the cells and canyon and the galleries was seven feet (2.13 meters) thick.  

Bottom of the B-Plant Canyon before concrete.jpg (982938 bytes)  221-T Canyon under Construction thick walls.jpg (293031 bytes)

Each building had a suspended flat concrete roof varying from three to four feet (0.91 to 1.22 meters) in thickness.  Construction joints were provided between each building section and expansion joints at frequent intervals.  The inside surfaces of the cells and pipe trench, removable cover blocks, the deck floor level in each canyon, and each second floor control gallery were painted with "Amercoat," an epoxy-based contamination fixant sealant, to reduce the porosity of the concrete surfaces.

            Each 221 Building structure was separated into two main portions - Galleries and Canyon, with the inside of the building being divided into 22 sections (for T-Plant) and 20 sections (for B-Plant).  Each section encompassed two cells.  Sections were 40 feet (12.19 meters) long with the exception of Sections 1, 2, and 20, which were 44 feet (13.41 meters), 43 feet (13.11 meters), and 43.5 feet (13.26 meters) respectively.  

          Inside the head-end of T-Plant, were two developmental equipment cells, A and B, having the same length as cells 1, 2, 3, and 4 [a total of 65 feet (19.81 meters) in length].  The essential difference between this testing laboratory and a standard T-Plant section was that each testing laboratory cell contained the equipment corresponding to that in two standard cell sections.  The head-end laboratory section also included a continuation of the basement, first and second floor galleries that ran the length of T-Plant.  However, these galleries turned at the head-end and continued across to the rear wall of the building.

   

4.1.4  Galleries

 

          The HEW canyon buildings were so designed that the control panel boards, chemical and service distribution, were located in three galleries, one above the other along the "front" side of the building; the west side in the case of T-Plant and the north side in the case of B-Plant.  The first gallery, at the basement level, was used principally for electrical distribution and control cabinets.  The first floor gallery consisted of a piping loft containing steam, water, air, and chemical headers as well as piping connections between the panel boards and weigh tanks on the second floor and through-wall cell piping.  The second floor gallery was the control center for the cell equipment, and was known as the operating gallery.  Each 40-foot building section constituted a separate unit, and were controlled by separate gauge boards in the operating gallery.  The gauge board panels were installed in a row along the barricade wall between the canyon and the galleries, with weigh tanks along both front and back walls of the gallery.  

221-T Gallery Level under construction.jpg (235467 bytes)    221-T Operating Gallery.jpg (49005 bytes)  221-T Chemical Storage along side.jpg (350747 bytes)

 

4.1.5  Canyon

 

          The lower portion of the canyon below the "deck" (ground) level contained 40 individual concrete cells having removable concrete cell-block covers.  The cell covers were constructed with overlapping, step-wise edges, to contain the radiation within the cells.  A 10-foot (3.05‑meter), 6‑inch (15.24‑centimeter) square exhaust duct ran along the back wall of the building paralleling the bottom of the cells and was connected by an underground concrete duct to the 291 Exhauster Buildings and Stacks for the removal of cell fumes.  Immediately above this duct was a pipe trench which also paralleled the cells, containing inter-connecting cell piping.  The pipe trench was also covered with removable, sectional concrete block covers.

            The construction of the cells was standardized as much as possible, to ease the maintenance problems as much as possible.  The sections having standard designs were 4, and 6 through 20.  Section 1 differed in that it was a large cell with two long openings for the immediate storage of partially processed material.  Section 2 contained two long openings of the same size, one of which centered over the railroad track where irradiated fuel elements were brought into the building, and the other which housed initial cell equipment.  A reinforced concrete railroad tunnel, extending 150 feet from the front sides of the buildings provided rail service to this section.  Section 3 differed in that the pipe trench ended opposite cell #5.  Section 5 differed in that cell #10 was much deeper, because it served as a collection point for drainage to the sewer section.  At T-Plant, the head-end sections differed in that the pipe trench terminated in a manner that would allow for future extension of the building if desired.  (Such extension did not happen.) 

 

 

4.1.6  Processing Equipment

hanford221u_cell_figure4.jpg (73909 bytes)    hanford221u_cell_figure3.jpg (88749 bytes)   hanford221u_cell_figure5.jpg (70178 bytes)

          The equipment installed in the cells consisted mainly of centrifuges and vessels with and without agitators, and connecting piping between cell walls and equipment.  Around the periphery of each cell were 42 flanged piping connections serving the cell equipment.  Special piping connectors were used allowing pipes, conduits, and instrument leads to be connected by tightening a single nut.  Vertical connectors were used for electrical connections only, and horizontal connectors were used for piping and instruments only.    

          The canyon portion of each Cell Buildings was served by an overhead bridge crane equipped with 75-ton and 10-ton hooks as well as four independent monorail hoists of one and one/half-ton capacities.  The crane cab was designed to contain special controls, observation and communication facilities in order to remove cell blocks, cell equipment and cell piping by remote control.  The canyons also each contained a second overhead bridge crane, 10-ton capacity for maintenance use only, when the building was completely shut down.

4.1.7  Stair Towers

          Four-story reinforced concrete stair towers were constructed along the front side of each 221‑T Building (eight in T-Plant and seven in B-Plant) to provide access to the three gallery levels and the crane-cab runway.  These stair towers also housed heating and ventilating equipment and rest rooms for the galleries.  Reinforced concrete labyrinthed stair towers were built along the rear sides (east side in the case of T-Plant and south side in the case of B-Plant), to provide access to the canyon portion of each building at the deck level.  T-Plant had ten such rear stair towers and B-Plant had nine.[lxxxvii]

4.1.8  224 Bulk Reduction Buildings  

          The 224 Buildings were constructed of reinforced concrete.  Each was a three-story frame structure with concrete and concrete block exterior and interior walls.  The front of each 224 Building was placed precisely 150 feet from the back of its corresponding 221 Building, and in line with the front of its process group's 222 Control Laboratory.  Each 224 Building contained a total of 21 rooms not including two stair towers, one closet, one janitor's closet, and an elevator "penthouse."  The overall dimensions were 60 feet (18.29 meters) 1 inch (2.54 centimeters) by 197 feet (60.05 meters) long, with a total area of 11,982 square feet (1 113.16 square meters).  Each building was 40 feet (12.19 meters) high for the majority of its length, but reached higher elevations over two stair towers and over the small penthouse area.

  wpe31.gif (626108 bytes)  224-T finishing in Dec 1944.jpg (338190 bytes)  224-T Transfer lines.jpg (231523 bytes)

          The foundation of each 224 Building was comprised of reinforced concrete walls with spread footings, reinforced concrete piers and beams, and concrete pads.  Each floor slab was reinforced concrete 4 to 12 inches (10.16 to 30.48 centimeters) thick.  Each roof consisted of flat reinforced concrete 5 to 12 inches (12.70 to 30.48 centimeters) thick, covered with built-up felt, gravel surfaced roofing, and containing 8 wood frame ventilators with meters.  The roof slabs were removable, so as to allow the movement of large equipment pieces in and out.

          Each 224 Building was essentially divided into two main sections:  the process cell section, and the office and operating gallery section.  The back side of the main structure contained the process cells and had one foot thick concrete walls with a balcony running around three sides.  The 27-foot (8.23‑meter) by 197-foot (60.05‑meter) process cell area contained five cells known as Cells A to E inclusive.  These cells were served by a hand-operated overhead crane.  Cells A through D measured 27 feet (8.23 meters) by 28 feet (8.53 meters).  Cell F measured 25 feet (7.92 meters) by 51 feet (15.54 meters), was L‑shaped, and had an office in one corner of it.  A glass enclosure was located in the cell against this office wall, where the partially finished product was collected for transfer to the 231-Z Isolation Building.  In Cell C, the right-hand portion was a pit which connected with an underground pipe tunnel that ran from the center line of Sections 13 and 14 in the corresponding 221 Building to each 224 Building.

          The floors in the cells were sloped to a trench along the wall, for gravity delivery to waste collection tanks.  The walls and floors in Cells A through E, and walls, floors, and ceilings in F Cells and its office were painted with Amercoat.  A mezzanine floor extended across the side facing the corresponding 221 Building.  Gauge boards and weigh tanks used in connection with Cell F were mounted on this mezzanine.

          One-foot (0.30‑meter) thick interior walls divided the process cell section of each 224 Buildings from the office and gallery section.  The "front" (offices and gallery) side of the main structure was reinforced concrete frame with 8-inch (20.32‑centimeter) concrete block panels and 8-inch (20.32‑centimeter) and 4-inch (10.16‑centimeter) concrete block partitions.  An elevator was installed adjacent to the No. 1 stair tower and was provided with an outside concrete loading platform to facilitate the movement of chemicals to and from trucks.  The first floor contained offices, a chemical storage room, and other service rooms.  The second floor was principally a pipe loft containing five concrete vestibules opposite each centrifuge platform.  All chemical and service lines entered the building on this level.  The third floor was an operating gallery that contained gauge boards, tanks, and instruments.[lxxxviii]

4.1.9  231 Isolation Building  

          The 231-Z Building was located in the western portion of the 200-West Area of the Hanford Site, midway between T-Plant and U-Plant.  Originally, this structure was a two-story, flat roofed, reinforced concrete, frame building with 8‑inch concrete block panels and 4‑inch (10.16‑centimeter) and 8‑inch (20.32 centimeter) concrete block partitions.  Overall dimensions were 147 feet (44.8 meters) by 189 feet (57.61 meters) 10‑inch (25.40 centimeters) by 24 feet (7.32 meters) 6‑inch (15.24 centimeters) tall, with a total of 27,964 square feet (2597.94 square meters).  A one-story ventilation and equipment room ran along the west end of the building.  The 231-Z facility had no windows.  

231-Z Exterior in 1944.jpg (331726 bytes)

          In World War II, the 231-Z Facility contained a total of 57 rooms including 20 laboratories, several process and chemical receiving and storage rooms, offices, change room facilities designed to accommodate 190 employees, air conditioning equipment, a distilled water system, ventilation and exhaust systems, and a compressed air system.  Six of the laboratories were known as "cell laboratories," and served as the major centers where the actual Pu isolation process was carried out.  All of the rooms except for one rest room were located on the first floor, with the second floor serving as a pipe and service loft containing duct work and filters for the ventilation and exhaust systems.

     The interior of the 231-Z Building was configured with two 8 foot (2.44‑meter) wide, north and south corridors, A and B; one on each side of the (6) cell laboratories with emergency exits to the outside of the building.  Corridors C and D ran east and west, connecting with corridor B.  Corridors E and F ran north and south separating laboratories and intersect corridors C and D.  Two concrete stairways led to the second floor, and below-grade piping led to a waste disposal system.  This piping was modified in 1948 to achieve additional control of 231-Z process wastes.

          The 231-Z Building foundations consisted of reinforced concrete piers with spread footings and concrete walls with spread footings.  Floors were reinforced concrete varying from 4‑inches (10.16‑centimeters) to 12‑inches (30.48 centimeters) in thickness.  The walls and ceilings of the cell laboratories and Vaults A and B were reinforced concrete 1 foot thick.  The roof was likewise reinforced concrete 4‑inches thick and was covered with built-up felt, gravel surface roofing containing numerous openings for intake and exhaust ducts.  The walls, floors, ceilings, and equipment in rooms 1 to 6, 8, 27, 31 to 45, Vaults A and B, and corridors A, B, C, D, E, and F were painted with "Amercoat" to obtain non-porous surfaces.[lxxxix]


 [lxxix].   Erickson, UNI-1437, Rev. 2, pp. 5-6, 10, V-1; Scott, UNI-1960, pp. 1-3, 13-17; Newby and Marshall, UNI-2109; Lyon, UNI-2110; Nelson, UNI-3422; Nelson, UNI‑3329; Zaloudek and Ruff, UNI-3653 (PNL-5924); Zaloudek and Ruff, UNI-38994 (PNL-5930); Lee, UNI-4193; Nelson, UNI-4191 Rev. 1; Alzheimer and Gonzalez, UNI‑4285; Martek, UNI-4263; Lyon, UNI-1986; Cummings, UNI-2063; Rainey, UNI‑2182; Conn, UNI-2227 Rev. 1; DeMaria, UNI-3481 Rev 1; Shoemaker and Fuller, UNI-21016; Reeves, UNI-610 Rev. 1; Lechelt, UNI-2925; Lattin, UNI-3333; Rasmussen, UNI-3583; Stauch, UNI‑4210; Linschooten, UNI-4148; Pope, UNI-4239; Smith, UNI-4253; Sullivan, UNI-4225.

 [lxxx].    Hanford Engineer Works, HW‑10475‑B, pp. 910-919.  (Note:  The exact fuel storage times used in World War II are not known.  Following the war, storage times lengthened in order to allow for additional decay (stabilization) of radioisotopes such as Iodine 131.)

 [lxxxi].   Foskett, HW-18208; Stark, HW-22824.

[lxxxii]. Watson, Brendel and Shields, WHC0EP-0477.

 [lxxxiii].  Harrison, DUN-7711.

 [lxxxiv].  Nelson, UNI-2046.

 

 

Home ] Up ] Search ] Contents ] Periodic Tables ]
Mild Introduction ] Chemist's Chemist ] Manhattan Project ] Seaborg's Journals ] Unexpurgated ] Photo Gallery ] T Shirts ] Links ] Swan Song ]

The Internet is a wonderful vanity press. It is a bully pulpit that costs the author of a website almost nothing. Therefore, it falls on the reader to exercise increased vigilence while browsing websites because the the layers of "editors" and "publishers" have been removed from the information transfer process and so that anybody can say most anything without regard for the facts or truth. This website is no exception. For that reason, I have tried to provide copies of enough of the original materials so that the reader can make his or her own interpretations of the source documents that led me to the conclusions expressed here. 

Last Edited 07/21/15 --Comments to Webmaster