PLUTONIUM PRODUCTION STORY AT THE HANFORD SITE:  PROCESSES AND

FACILITIES HISTORY

 

 

Michele Gerber, Ph.D.

 

June 1996

 

 

ABSTRACT

 

 

          This document tells the history of the actual plutonium production process at the Hanford Site.  It contains five major sections:

 

                  Fuel Fabrication Processes

                  Irradiation of Nuclear Fuel

                  Spent Fuel Handling

                  Radiochemical Reprocessing of Irradiated Fuel

                  Plutonium Finishing Operations

 

          Within each section, the story of the earliest operations is told, along with changes over time until the end of operations.  Chemical and physical processes are described, along with the facilities where these processes were carried out.  This document is a processes and facilities history.  It does not deal with the waste products of plutonium production.

 

                                                               TABLE OF CONTENTS

 

1.0  FUEL FABRICATION PROCESSES     58

1.1  SINGLE PASS REACTOR FUEL FABRICATION 58

1.1.1  Solid Uranium Metal Fuel Produced 58

1.1.2  The Overall Process          59

1.1.3  Canning   60

1.1.4  Canning Tests       61

1.1.5  Additional Chemical and Hazardous Components      62

1.1.6  Process Changes   62

1.1.7  313 Building Expansion Under Eisenhower/Switch to Lead-Dip Process           63

1.1.8  Projection Fuel Elements    64

1.1.9  End of Single-Pass Reactor Fuel Making      64

1.1.10  Other 313/314 Building Processes 65

1.2  N REACTOR FUEL FABRICATION      67

1.2.1  The 333 Fuels Manufacturing Building         67

1.2.2  Co-Extrusion Process         68

1.2.3  Other Processes in the 333 Building            69

1.2.4  The Waste Acid Treatment System (WATS) Process            69

2.0  IRRADIATION PROCESSING AT THE HANFORD SITE           71

2.1  HANFORD'S SINGLE PASS REACTORS          71

2.1.1  Historic Significance of B-Reactor    71

2.1.2  Single-Pass Reactor Buildings         71

2.1.3  Operation of the Single-Pass Reactors         73

2.1.4  Change and Experimentation in Production Process  73

2.1.5  Graphite Expansion Early Problem   74

2.1.6  Increased Power Levels/Production 74

2.1.7  Operating Challenges at Higher Power Levels           75

2.1.8  Reactor Upgrades for Increased Production 77

2.1.9  End of Single-Pass Operations        78

2.2  N REACTOR OPERATIONS   79

2.2.1  105 N Building and Reactor            80

2.2.2  N Reactor Operating Changes and Challenges          81

3.0  SPENT FUEL HANDLING AT THE HANFORD SITE       83

3.1  ORIGINAL LAG STORAGE PRACTICES           83

3.2  212 LAG STORAGE BUILDINGS CLOSE          83

3.3  CLOSURE/RE-OPENING OF FUEL STORAGE BASINS   84

4.0  RADIOCHEMICAL SEPARATIONS PROCESSING       86

4.1  THE BISMUTH-PHOSPHATE PROCESS       86

4.1.1  Start-up of Radiochemical Processing at HEW 86

4.1.2  T, B, and U Process Groups       86

4.1.3  Original Separations Buildings   86

4.1.4  Galleries 87

4.1.5  Canyon  88

4.1.6  Processing Equipment   88

4.1.7  Stair Towers      89

4.1.8  224 Bulk Reduction Buildings    89

4.1.9  231 Isolation Building    90

4.1.10  The Bismuth-Phosphate Process        91

4.1.11  Dissolving        92

4.1.12  Extraction        92

4.1.13  Decontamination         92

4.1.14  224 Bulk Reduction Process    93

4.1.15  231 Isolation Process 93

4.1.16  Earliest Operations     93

4.1.17  Early Process Changes            94


THE PLUTONIUM PRODUCTION STORY AT THE HANFORD SITE:  PROCESSES AND

FACILITIES HISTORY

 

 

                                                   1.0  FUEL FABRICATION PROCESSES

 

 

1.1  SINGLE PASS REACTOR FUEL FABRICATION

 

 

1.1.1  Solid Uranium Metal Fuel Produced

 

          The nuclear fuel fabrication processes employed at the Hanford Site to manufacture plutonium (Pu) for defense purposes essentially produced solid uranium (U) metal fuel elements, jacketed in aluminum-silicon (later Zircaloy-2)a coats.  Although some variations were introduced, the solid metal fuel type was not replaced by powdered or pelletized fuel forms, nor by mixed oxide (MOX) fuel blends for the production of defense-grade Pu-239.  Moreover, the fuel-making processes used at the Hanford Site for defense production all were unique and prototypical at the time they were initiated.  Thus, they qualify under criteria of the National Historic Preservation Act (NHPA) as historic processes.

 

1.1.1.1  Original Fuel-Making Buildings.  The original fuel-making process employed at the Hanford Engineer Works (HEW- World War II name for the Hanford Site) was known as the "triple-dip" process.  It took place in two buildings in HEW's 300 Area, known as the 313 Metal Fabrication Building and the 314 Press Building (also known as the Metal Extrusion Building).  Both buildings were constructed of structural steel framing, had concrete block walls and concrete slab floors, and sat on reinforced concrete foundations.  The 313 Building had a precast concrete slab roof with tar and gravel surface, and interior partitions made of concrete block and concrete brick.  The 314 Building had a corrugated asbestos roof with a 36‑inch (91.44 centimeters) continuous roof ventilator extending nearly the entire length of the building.  Interior walls consisted of concrete block with 3/16‑inch asbestos board on some interior partitions.[i]

 

          The original 313 Building, completed in the Autumn of 1943, was rectangular in shape, with overall dimensions of 199.5 feet (60.8 meters) by 65 feet (19.8 meters) by 20 feet (6.09 meters) (high).  However, eight subsequent additions made in late 1943 and in 1944 brought the overall dimensions to 199.5 feet (60.8 meters) by 182.5 feet (55.6 meters) by 20 feet (6.9 meters) (high), with a total area of approximately 36,000 square feet (3,344.4 square meters).  The continual early additions were caused by process improvements and changes in the very new, untried, and unique uranium fuel fabrication activities being carried out in the facility.  According to prime construction contractor DuPont Corporation:  "In the construction of the 313 Building, the first equipment to go into operation was known as the experimental line.  This line was set up specifically for experimental purposes...[and] was dismantled and moved to other portions of the...Building."[ii]

 

          The first 313 Building addition, on the east side, provided additional space for furnaces and presses, and the second, on the west side, provided a tool room and shop.  The third addition ran the entire east side of the building, and allowed space for welding booths and jacket (can) washing.  The fourth addition, on the northwest corner, furnished an electrical control room, and the fifth addition, along the west side, included a locker room, women's rest room, and shower room.  (The locker and shower rooms later were eliminated in favor of a storeroom.)  The sixth addition was again on the northeast corner of the facility, and provided more space for can washing.  The seventh addition, on the southeast of the building, allowed for a second canning process section and for "recovery" (uranium scrap recycling) process equipment.  However, this latter equipment soon was moved to the nearby 314 Press Building.  The eighth and final addition of WWII was on the northeast corner, and furnished space for a third canning process section.[iii]  The 313 Building contained numerous electrical furnaces and metal presses; three fuel canning areas; a welding area; a can cleaning area; a control room; various supply tanks; a tool room and shop; and various offices, storerooms, and sanitary rest rooms.

 

          The 314 Press Building had original overall dimensions of 199.5 (60.8 meters) feet by 90.5 feet (27.58 meters) by 40 feet (12.19 meters) (high) with an area of about 17,000 square feet (1579.35 square meters).  It contained a 1,000‑ton extrusion press, electric furnaces, a rod-straightening machine, a 7.5‑ton overhead crane, an autoclave area, a control room, a shop and repair area, pumping units for the press, and various offices and sanitary rest rooms.  Outside, there was a 12‑foot (3.66 meter) by 18‑foot (5.49 meters) concrete and steel platform north of the building.  Gas cylinders were located outside along the north wall.[iv]

 

 

1.1.2  The Overall Process

 

          Hanford's original fuel-making processes can be summarized as follows:  It began in the 314 Building, where uranium that arrived as billets was heated in a muffle‑type furnace with an interior, inert gas atmosphere.  (The helium or argon atmosphere was used to reduce the oxidation of metal during heating.)  The uranium was then transferred through a closed passageway to the extrusion press, which also operated in an inert atmosphere.  After being extruded, the rods were outgassed, straightened, and sent to the 313 Building for machining and jacketing.  In the 313 Building, U fuel rods were machined into fuel cores in lengths of either 4 inches (10.16 centimeters) or 8 inches (20.32 centimeters), with 1.3-inch (3.3 centimeters) inner diameters.  Known as "slugs," these cores were "canned" or jacketed into finished elements, and then tested and inspected in this building.

 

          Details of the HEW fuel-making process provide valuable insights:  The earliest uranium for the fabrication of reactor fuel arrived at the HEW in October 1943 as extruded rods.  The rods were delivered to the Riverland Yards.  The Riverland Yards were an official part of HEW and were located just east of the Midway power substation (just west of the 100-B Reactor Area).  Because railroad track had not yet been completed to the 300 Area, the rods were taken by rail to the Hanford Construction Camp about 20 miles (32.19 kilometers) north of Richland, and then by truck to the 300 Area.  Once railroad service to the 300 Area was connected in January 1944, uranium was delivered to the fabrication area by rail.

 

          Newly arrived U rods were unpacked and visually inspected (in sample amounts) for cracks and for overall dimensions.  A random amount from each lot was taken to the 305 Test Pile Building just west of the 313 Building, and irradiated at a low level to check for warping, cracking, and embrittlement under irradiation.  If the sample withstood the process in good form, the entire lot was accepted.  Beginning in December 1943, the first uranium fabrication operation at HEW was machining, in which bare uranium rods were lathed down to specific core dimensions in the 313 Building.  The following month, operators began degreasing the machined cores before inspection, using a commercial product that contained primarily trichloroethylene, Detrexa, a solvent degreaser.  Core canning operations actually began in the 313 Facility in March 1944.

 

          In the 314 Building, autoclaves for fuel element testing started to operate in July 1944.  A scrap recovery process began the following month.  Outgassing and straightening operations started in the 314 Building in September 1944, but HEW's uranium rods still were being extruded offsite.  Beginning in November 1944, uranium was transported to HEW as billets, which were stored until the extrusion process began to operate in the 314 Building in January 1945.  The press testing phase lasted into mid‑spring, and then fuel operations commenced.  Greater confidence in personnel performance ended shift work in the metal preparation buildings in June 1945, and work proceeded on a straight, 6‑day-per-week schedule.  From that time until 1948, a complete cycle of metal preparation occurred at HEW.  The uranium billets went to the 314 Building for extrusion, outgassing, and straightening, then to the 313 Building for machining, canning, and initial inspection, and then back to the 314 Building for autoclave and radiograph testing.[v]

 

 

1.1.3  Canning

 

          The original fuel canning process tried at HEW involved the use of an electric heater press, known by workers as the "whiz‑bang," to heat and bond the uranium fuel cores to their aluminum jackets.  However, the heaters burned out frequently, did not heat the elements and cans to consistent temperatures, and did not produce a uniform bonding.  This problem was serious because nonuniform bonding caused thin places in the jacketing that, under irradiation, heated up more than other places.  These "hot spots" could cause fuel element ruptures in the reactors.  By August 1944, the uranium fuel cores were being jacketed in a triple‑dip method that consisted of bathing them in molten bronze, tin, and then a molten aluminum‑silicon mixture.  The bronze used in this process at HEW was relatively high in tin content (53% tin and 47% copper), and the bronze bath itself had a flux cover composed of barium chloride, potassium chloride, and sodium chloride.  As fuel cores were dipped into this mixture, they acquired trace coverings of all of these substances.

 

          Initially, the bare uranium cores were cleaned by passing them through a trichloroethylene vapor degreaser, then through a nitric acid tank, two rinse tanks, and a hot air dryer.  The nitric acid rinse was known as "pickling" the slugs.  Meanwhile, a steel "sleeve" that would surround each can during the dipping process was cleaned in sodium hydroxide, and aluminum end caps and cans were cleaned in a sodium dichromate solution followed by a methanol rinse.  The bare uranium cores were dipped in a bronze bath to heat them to a uniform temperature within the uranium beta phase (660 °C to 770 °C), and then placed in a tin bath to (1) cool them into the uranium alpha phase (less than 660 °C) and (2) remove excess bronze.  Next they were centrifuged to throw off excess tin.  Then the cores were immersed quickly in an aluminum-silicon brazing bath (also in the uranium alpha phase), and water quenched.  The various heating and cooling procedures were done to randomize the uranium grains, thus inhibiting the uranium "growth" (expansion under irradiation) problem.  After water quenching, the steel sleeve was pulled away and cleaned with sodium hydroxide and soap to remove any remaining aluminum-silicon.  The sleeve then could be reused many times.  The thickness of the residual end cap on the element was then measured with a fluoroscope and marked with a punch to indicate the amount that needed to be removed in subsequent end machining.  Identification numbers were stamped on the can base end, and the braze line on the end cap was tungsten inert gas (TIG) welded to seal the porous braze to the end cap and can.  A final etching in nitric acid completed the procedures.

 

 

1.1.4  Canning Tests

 

          Three tests followed the canning process.  The first, the frost test, consisted of spraying the can with acenaphthene mixed with carbon tetrachloride (CCl4).  The canned element was then placed into an induction coil to heat its surface.  If there was a gas bubble or a nonbonded spot, this spot would become shiny, and the element then would be rejected and sent back through a recycling process.  If the bond was good, the acenaphthene was removed with trichloroethylene, and the element was inspected in one of several autoclaves located in the 314 Building.  In that inspection, the canned element was placed into a steam autoclave, which operated at about 100 pounds (45.36 kilograms) per square inch gauge (psig) at 175 °C for more than 20 hours, to reveal any pinholes or incomplete welds.  Water from the steam would be conducted through any such openings, and the uranium core would expand rapidly, resulting from the formation of a uranium oxide (UO2) compound known as U3O8, and split the aluminum can.  If an element passed the autoclave test it then underwent a final radiograph (X‑ray) test in the 314 Building, to detect porosity in the end weld bead.  Any porosity could have become a pathway for water to contact the uranium fuel and cause the element to rupture.[vi]

 

 

1.1.5  Additional Chemical and Hazardous Components

 

          In addition to the above‑mentioned chemicals, other hazardous substances were used routinely in early HEW fuel fabrication processes.  Aluminum cans and caps were cleaned using first trichloroethylene, then Duponol-M-3a (an industrial soap), phosphoric acid, and various rinses including methanol.  Steel sleeves were cleaned in sodium hydroxide and soap.  Caustic cleaners popular at HEW included Aluminux and Diversey‑415b, both containing primarily sodium dichromate.  Sodium hydroxide and sodium nitrate were used to strip aluminum and braze off the rejected uranium cores.  An intermetallic compound layer of uranium and copper (specifically UCu5) on the rejected cores was removed by using hydrofluosilicic acid.  Acetone and methyl alcohol (methanol) were used as all‑purpose cleaning and drying agents.

 

 

1.1.6  Process Changes

 

          In 1948, the extrusion press in the 314 Building was excessed, and HEW began receiving rolled uranium rods from an offsite commercial mill.  The rolling process seemed to offer metallurgical advantages, because the uranium could be processed at lower temperatures, which induced less oxidization and produced smaller and more random grains within the metal.  This type of grain within the uranium avoided the "pimpling and dimpling" of fuel rods, a persistent problem in early fabrication efforts.  It was also a less expensive process.  From 1950 to 1951, a rolling mill was procured and installed in the 314 Building, to save the costs of shipment to offsite mills.  However, this mill was relatively small, and the rolling operation was transferred to a large facility constructed at the Feed Materials Production Center (FMPC), an Atomic Energy Commission (AEC) site in Fernald, Ohio, in 1952.  Thereafter, no extruding or rolling operations were conducted at the Hanford Works (HW - the peacetime name given to HEW in 1947 by the AEC) in connection with the fabrication of fuel elements for single‑pass reactors.  The 314 Building process continued to operate for the purposes of straightening uranium rods, providing autoclave and radiograph testing of canned elements, and providing uranium scrap processing operations.[vii]

 

 

1.1.7  313 Building Expansion Under Eisenhower/Switch to Lead-Dip Process

 

          In 1954, the 313 Building underwent a major remodeling and expansion, reaching a total size of 182.5 feet (55.63 meters) by 486 feet (148.13 meters), with a total area of 76,633 square feet (7119.44 square meters).  At that time, much contaminated equipment and other solid wastes from this building and its immediate surrounding area and from the 303 fresh fuel warehouses were buried.  The remodeling occurred at the time that fuel canning technology in the 313 Building switched from the triple‑dip process to the new lead‑dip process.  Lead‑dip consisted of immersing the uranium fuel cores in a duplex bath (molten lead covered with molten aluminum-silicon) to preheat the cores in the uranium alpha phase.  This step formed an intermetallic compound of uranium and lead (UPb or UPb3) on the core.  It was followed by a molten aluminum-silicon bath (also in the uranium alpha phase) to braze and bond the cores to the aluminum cans and caps.  This process allowed the first canning bath to occur at a lower temperature (lower than 660 °C) because the uranium cores already had been beta heat treated in a molten salt bath at the FMPC.  However, the new method introduced a great deal more lead and other heavy metals into 313 Building waste streams, because approximately 30,000 fuel elements were canned per week during the years of peak single‑pass reactor operations at HW (1955‑1964).  At about the same time that the lead‑dip process replaced the triple‑dip method, an ultrasonic test replaced the frost test, which eliminated the use of acenaphthene and CCl4.  Concurrently, the majority of testing autoclaves were removed from the 314 Building and placed in the north end of the 313 Building.

 

1.1.7.1  Hot Die Size Process.  In the early 1960's, just before the eight single‑pass reactors at HW began to close, experiments were under way in the 304, 3716, and 313 Buildings with a new canning procedure known as the Hot Die Size Process.  Also termed the "nickel‑plate" procedure, this operation plated uranium fuel cores with nickel, using nickel sulfate, nickel chloride, and boric acid.  It included standard fuel fabrication cleaning, degreasing, etching, and testing chemicals and processes.  Although the Hot Die Size method was tested successfully, it was not implemented on a large scale, because of the impending closures of HW's eight original reactors.[viii]

 

1.1.7.2  Cored and Internally and Externally Cooled (I&E) Fuel Elements.  In the 313 Building, additional fuel fabrication process changes during the 1950's and early 1960's included the manufacture of cored fuel rods beginning in 1954, internally and externally cooled (I&E) fuel rods beginning in 1957, and projection fuel rods in the early 1960's.  The cored rods, hollow elements with an aluminum plug at either end, bonded to the uranium with an aluminum-silicon braze, were designed to give the uranium an inner space in which to expand during irradiation.  The early, solid fuel elements were experiencing a troublesome level of distortion, and subsequent rupture, in HW's production reactors.  However, the cored fuel elements frequently developed cracks in both the uranium and the aluminum plug areas, and they were discontinued in 1957.  The I&E fuel elements, tried next, had a tubular hole down the middle, allowing cooling water to run both around and through them in the reactors.  Projection fuel elements, with small fins protruding from their sides, were of two types:  the bumper type had six short projections for use in ribbed process tubes, and the self‑supporting type had eight projections for use in ribless process tubes.

 

 

1.1.8  Projection Fuel Elements

 

          The switch to projection fuel rods represented yet another attempt to solve the fuel element rupture problem then plaguing Hanford's eight single‑pass reactors.  Power and fuel exposure level increases throughout the late 1950's and early 1960's had brought reactor operating temperatures to a point that seriously augmented fuel rod ruptures, with resultant increases in contamination released to the Columbia River.  Post‑irradiation examinations of failed I&E fuel elements showed that only about 20% of the failures resulted from fuel element "quality deficiency," while 80% resulted from longitudinal corrosion attack caused by warp.  Known as "side hot‑spot" ruptures, these failures were caused by positioning of the fuel rods in the process tubes.  The new projection fuel elements, first tested in 1961 in reactors at HW, were manufactured in the 313 Building through the use of ultrasonic welding.  Canned fuel elements first were dipped in a tank to deposit an Ivorya soap film, useful in achieving a good weld.  After the projections were welded, the soap film would be rinsed off in a three‑compartment rinse using standard fuel fabrication chemicals and degreasers.[ix]

 

 

1.1.9  End of Single-Pass Reactor Fuel Making

 

          Fuel element preparation activities for the single-pass reactors ended in the 313 and 314 Buildings in 1971, when the last of these reactors closed.  The 314 Building was modified in the 1970's and was used for a variety of research projects and crafts services.  The majority of the fabrication equipment for single-pass reactor fuel elements was removed from the 313 Building between the mid‑1970's and the mid‑1980's.  However, the south end of the 313 Building continued to house major functions in support of N Reactor fuel production.  Among these functions were the receiving and inspection of uranium billets and other components used to make N Reactor fuel elements and the chemical passivation of spacers from N Reactor, the casting and machining of copper‑silicon preshape components used in N Reactor fuel elements (beginning in 1973), and the neutralization and handling of non‑uranium‑bearing acid wastes from N Reactor fuel fabrication processes in the 333 Building.  Finished N Reactor fuels and fabrication components, tools, and miscellaneous supplies were stored in the north end of the 313 Building from 1971 to 1987, and an Engineering Development Laboratory, including facilities for working with uranium, was established in the structure in the 1970's.  In 1983/1984, a Suttonb extrusion press was purchased and placed in the 313 Building as a backup for the extrusion press operating in the 333 Building performing N Reactor fabrication work.  However, the shutdown of N Reactor operations in December 1986 precluded use of the Sutton press.

 

 

1.1.10  Other 313/314 Building Processes

 

          Over the years, several other ancillary or off-shoot processes have taken place in the 313 and 314 Buildings.  Among these have been U scrap recovery operations, experimental and/or small-scale fuel making ventures, and waste treatment procedures.  From its earliest days, concern of the Manhattan Engineer District (MED - earliest federal management agency over HEW) about the adequacy of uranium supplies brought strict policies that mandated the reclamation of all possible uranium scraps at federal atomic sites.  During the earliest fuel fabrication operations at HEW, difficulties with early fuel canning techniques produced thousands of rejected cores, lathe turnings, metal oxides that formed when canned slugs failed in autoclave tests, and other scraps by mid-1944.  That June, Du Pont reported that "all available space" around the 313 and 314 Buildings was filled with cans of scrap, and the fabrication area fence had to be moved about 30 feet (9.14 meters) east of fresh fuel storage building 303‑J to allow for more storage space.  Several can fires occurred.  Beginning with the startup of extrusion press tests in January 1945, extrusion butt ends, oxides, and container residues collected, along with acids from the slug pickling process and from the slug recovery process.[x]

 

          At first, the various types of scrap were shipped to offsite reclamation processing centers.  By 1946, however, the volume of uranium scraps accumulating and the expense and fire and security hazards of shipment brought a change in policy at HEW.  A "chip recovery" operation began in the 314 Building.  It operated only a few days a month and involved collecting all chips and turnings from machining operations, sorting them, breaking them into small pieces, washing, drying, and then pressing them into briquettes.  At first the briquettes themselves were shipped offsite.  In May, however, the MED ordered briquetting to be discontinued, due to a number of uranium chip fires within the centrifuging step at other sites.  A "melt plant" was established in the 314 Building in late 1947.  In that process, "new" uranium could be made by combining uranium tetrafluoride (UF4 or "green salt") and either calcium chips or magnesium chips.  This mixture was placed in a dolomite-coated steel vessel, heated until free molten uranium separated from magnesium fluoride or calcium fluoride, and then allowed to cool.  The molten uranium settled into large buttons shaped like Derby hats (called "Derbies" by HW workers).  Slag was jackhammered off the Derbies, which were mixed with the recycled uranium scraps and briquettes, melted in a vacuum furnace, and cast into ingots.  These ingots were then rolled into new uranium rods, either offsite or at Hanford, and used to make additional fuel rods.

 

          In the spring of 1946, an additional scrap recovery operation known as the "oxide burner" began on the north side of the 314 Building.  All uranium‑bearing dust and particulate matter that could be collected from the fuel fabrication facilities, as well as the tailings or settlings from washes and quenches, was burned to convert it to oxide (powder) form.  The UO2 was then collected in 5‑gallon (18.93 liters) buckets for compact shipment offsite.[xi]

 

          From the outset of chip recovery operations in 1946, HW's Health Instruments (H.I.) Division detected serious radiological problems with this process.  Throughout 1946 and 1947, monitors reported that oxide burner operations were really spreading metal dust and oxide around the 314 Building, producing airborne contamination samples over tolerance.[xii]  In December 1947, the oxide burner operation moved to a separate building north of the 314 Building.[xiii]  Both melt plant and oxide burner operations were phased out at HW between 1952 and 1954.  The burnout of slag from used melt crucibles was completed, and the furnace was excessed to the 300 Area Burial Grounds by late summer 1954.  Thereafter, solid uranium scraps at HW continued to be collected, stored, and combined with solids collected from neutralized, uranium‑bearing waste acids and processed through a press‑and‑frame filter press in the south end of the 313 Building.  Together, all of these scraps were slurried into sodium diuranate, stored in the 303 Buildings area, and shipped in barrels to the FMPC.[xiv]

 

          From 1944 through the 1950s, bismuth fuel targets welded into nonbonded aluminum cans, irradiated to make polonium‑210 in 100 Areas production reactors, were fabricated in the 313 Building.  Polonium‑210 was the initiator in atomic (pre‑hydrogen and non-hydrogen) weapons explosions.  An even larger number of lead-cadmium fuel rods, also welded into nonbonded aluminum cans, were produced for use as "poison" elements in the 100 Areas reactors and in the 305 Test Pile.  The term "poison" refers to the ability of these neutron absorbing metals to slow down or even kill (control) nuclear chain reactions.  The production of lead‑cadmium fuel rods continued throughout the years of single‑pass reactor operations (through 1971).  Additionally, lithium-aluminum alloy fuel targets, manufactured for the P‑10 project at Hanford's 100‑B Area to produce tritium for the world's first hydrogen weapons tests, were canned in nonbonded aluminum cans in the 313 Building from 1949 to 1952.

 

          During the early 1950s, a number of attempts were made to fabricate and jacket metallic thorium fuel targets in the 313 Building to produce uranium‑233.  Many problems connected with the rapid formation of a thick coat of oxide on the thorium metal targets led to experiments with a variety of bonding methods and coatings.  Eventually, thorium oxide (ThO2) powder and wafer fabrication was carried out in the nearby 3722 and 3732 Buildings in the late 1960's.  Beginning in the late 1950s and continuing until 1971, a process to electrolytically anodize the aluminum "spacers" (dummy fuel elements) used in the single‑pass reactors (to create a protective aluminum oxide [Al203] coating) was added in the 313 Building.  The passivation of N Reactor steel spacers to reduce rust formation also took place in the 313 Building from the mid‑1960s through the mid‑1980s.[xv]  Also, highly enriched uranium-aluminum fuel cores, used as driver elements in the early tritium production program and in a mid‑1960's uranium‑233 production program in the N Reactor, were manufactured and canned in nonbonded aluminum cans in the 313 Building.

 

          Beginning in 1954, waste acids containing recoverable amounts of uranium from the 313 and 333 Buildings were routed to designated tanks in the 313 Building, neutralized, routed to another tank, and passed through a press-and-frame filter press.  The precipitate remaining on the filter press was known as "C‑6" sludge, and was collected and placed in barrels for shipment to the FMPC.  The centrifuging operation, along with waste acid storage tanks, anodizing tanks, and the filter press used to separate sodium diuranate from uranium‑bearing, neutralized wastes, was located in the south end of the 313 Building.  A process to recover uranium cores from rejected, lead‑dip canned fuel elements also began in the south end of the 313 Building in 1954.  Boiling sodium hydroxide was used to remove the intermetallic compound layer of lead and uranium from the elements.  Beginning in 1975, the 313 Building played a key role in a new Waste Acid Treatment System (WATS) process that was emplaced in connection with the nearby 333, 334 and 334A Buildings.  The WATS process operated until 1987.

 

 

1.2  N REACTOR FUEL FABRICATION

 

          The fuel-making process for the New Production Reactor (N Reactor) was very different from that used to make fuel for Hanford's single-pass reactors.  Soon after funding was secured for N Reactor in 1958, a high pressure heat transfer apparatus was emplaced in the 189/190-D Building, a converted World War II pumphouse in the Hanford Site's 100-D Area.  Its purpose was to test a new, N Reactor fuel concept being developed in the 306 Metallurgical Pilot Plant, a 300 Area building dedicated to fuel manufacturing experimentation.  The concept first tried for N Reactor fuel was a wire-wrapped, seven-element cluster of long, thin fuel rods spaced together in a horizontal flow tube.  Each individual element was only 0.625 to 0.704 inches (1.59 to 1.79 centimeters) in diameter, and was 35 to 45 inches (88.9 to 114.3 centimeters) long.  As such, the heat transfer and flow properties of these elements were very different from those of the solid U or I&E fuel elements previously used at Hanford.  An understanding of every characteristic of the new elements, including subcooled and boiling burnout and pressure drop parameters, was essential if they were to be recommended for N Reactor use, so trials continued throughout 1959.[xvi]  However, attention soon turned to yet another new concept developed in the 306 Building.  This idea, of a co-extruded tube-in-tube fuel element design, eventually was adopted for N Reactor.  A full-scale, experimental heat transfer test section that simulated the downstream half of a tube-in-tube charge in N Reactor was built on the mezzanine of the 189/190-D "flow laboratory."[xvii]

 

 

1.2.1  The 333 Fuels Manufacturing Building

 

          In the meantime, construction of the new 333 Fuels Manufacturing Building, to produce N Reactor fuel elements on a plant scale, was being constructed just east of the 313 and 314 Buildings.  Building design itself did not depend on knowing exactly which manufacturing process would be used, but once the co-extrusion process was selected, the equipment eventually procured and constructed in the 333 Building was unique.  The 333 Fuels Manufacturing Building itself was constructed of steel frame with double metal insulated panel exterior walls and lightweight metal panels for interior partitions.  The foundation and floors were poured concrete.  The roof consisted of insulated metal paneling covered with felt and roll tarpaper and a tar and gravel surface.  The roof was refinished in 1962.  The structure was 300 feet (91.44 meters) by 140 feet (42.67 meters), with a total area of 48,817 square feet (4535.25 square meters).  In 1980, in response to anticipated increases in production, a small addition was placed on the northwest corner of the 333 Building.  It consisted of two stories; the ground level an open bay shop and the second story for offices.  The addition was 33 feet (10.06 meters) by 104 feet (31.70 meters), and runs from the HVAC (heating, cooling and ventilating) supply units on the west side of the building to the north exterior wall.

 

          A majority of the 333 Building was a large, one story, open bay housing large machinery for fuel-making, but the structure also contained two mezzanines.  The larger mezzanine ran along the east wall and housed distribution equipment and offices.  The smaller central mezzanine housed ventilation equipment for the chemical bay.  Air conditioning and heating of the building originally was accomplished with steam heat and evaporation cooling forced air equipment located in a 30-foot (9.14 meters) by 75‑foot (22.86 meter) enclosure adjoining the west side of the building.  During 1979-80, some energy conservation upgrades and cleanouts were made in this system.  New heat recovery systems were installed.  The 333 Building has always been equipped with electrical fire detection mechanisms and an automatic sprinkler system.  The co-extrusion process was carried out with various equipment pieces, but the most prominent and unique of these was a Loewy Press that actually pressed all of the fuel components (U core and all of the cladding components) together in one unit.  Each N Reactor fuel element was 26 inches (66.04 centimeters) long, weighed approximately 52 pounds (23.59 kilograms), and had a tube-in-tube configuration with a coolant channel running down the entire length of the element.  Projections also were welded onto each element, as the N Reactor process tubes were smooth or "ribless."  The co-extrusion process provided a better, more uniform bond between core and jacket that had been possible with older methods based on dipping.  The new method was beneficial in smoothly cladding the inner and outer tubes so that they would fit together without developing "hot spots."

 

 

1.2.2  Co-Extrusion Process

 

          The co-extrusion process began with inspection and cleaning of copper and copper-silicon pre-shapes and backing plates used in the process.  The cleansing agents were nitric acid, nitric hydrofluoric, and chromic nitric sulfuric acid.  Next, cladding components made from Zircaloy-2 were degreased, rinsed in nitric and hydrofluoric acid, and dried with forced-air heating.  In the meantime, U billets were degreased with perchloroethylene, etch with nitric acid, rinsed, dried and inspected.  Next, the copper, copper-silicon, Zircaloy‑2, and U components were assembled and welded into a billet assembly.  This assembly was evacuated of air, leak tested, sealed preheated, and then co-extruded (squeezed together) in the Loewy Press.  As the process specifications for this step emphasized:  "The quality of the extruded tube is dependent upon many things, not the least of which is skill, care, effort,and precision that are put into the co-extrusion operation."[xviii]

 

          The process of cleaning, degreasing, etching and drying components, then assembling and pressing them, was repeated for both the outer (larger) and inner (smaller) tubes that made up the tube-in-tube configuration.  The extruded tubes then exited the press to a roll-out table where they were rolled continuously for at least six minutes to prevent tube deformation and non-uniform cooling.  Next they were sectioned to the specified length, and the ends were machined to create fuel sections or elements.  Nitric acid was used to remove copper silicon residues, and nitric sulfuric acid was used to chemically mill (i.e., dissolve away) excess uranium on fuel element ends.  Elements then were etched with nitric hydrofluoric and nitric acid, and brazed with an etched braze ring material consisting of Zircaloy-2 alloyed with about five percent beryllium.  (This braze material previously had been degreased and etched.)  The brazed elements were heat-treated in a molten salt bath to randomize the U grain structure to prevent preferential grain growth that could rupture the elements in the reactor.

 

          The next step in the process was to weld projections or supports onto the fuel elements.  Eight lengthwise protrusions were attached to the outer surface of each fuel element, evenly spaced around its diameter.  This configuration allowed cooling water to circulate optimally around the elements, without creating hot spots where the sides of elements rested too close to the inner walls of the process tubes.  After projections were welded onto the elements, the two tubes (inner and outer) had to be attached together.  Support hardware was attached to the outer surface of the inner tube, and locking hardware was affixed to the inner surface of the outer tube.  The two tubes then were given a final nitric hydrofluoric acid etc, separately tested in autoclaves, inspected, assembled and interlocked, and stored as finished fuel.  The coextrusion process was carried out continuously in the 333 Building from 1960 until December 1986, reaching a peak volume of approximately 250 finished fuel elements per week in the mid-1980s.[xix]

 

 

1.2.3  Other Processes in the 333 Building

 

          From 1965 to 1967, the 333 Building performed autoclave testing, final etching with nitric‑hydrofluoric acid, and inspection of special lithium aluminate fuel targets made in the nearby 3722 Building for the production of tritium.  Highly enriched (2.1% uranium‑235) uranium driver fuel elements for tritium programs also were made in the 333 Building from 1965 to 1970.

 

 

1.2.4  The Waste Acid Treatment System (WATS) Process

 

          In 1971, a study of radioactive releases and special materials accounting practices identified several areas of concern in 333 Building operations.  Among these concerns were the amounts of contaminated gaseous, particulate and liquid discharges, and the need for expansion of monitoring and sampling systems.  Partly in response to these concerns, the Waste Acids Treatment System (WATS) process was developed, a new system to catch and neutralize waste acids from the structure's fuel-making processes.  In 1973, the WATS began partial operations to treat waste acids from 333 Building operations.  It operated for four months in 1973 and became fully operational in January 1975.  The 300 Area WATS process represented a method to prevent 333 Building fuel fabrication bulk waste acids from discharging to the 300 Area process sewer.

 

          Tanks and control instruments for the WATS system were located in and below the 334‑A Waste Acid Storage Facility, a small steel frame structure that was moved in close to the 333 Building, from Hanford's 200 Area.  The portion above grade was used for general storage of products and absorbents, and the portion below grade contained three tanks seated in a reinforced concrete pit 18.5 feet (5.64 meters) by 18.3 feet (5.58 meters) by 10 feet (3.05 meters) (deep).  Additional tanks and piping components for the WATS system were located in the 313 Building, the 333 Building, the 334 Chemical Handling Facility next door to the 333 Building, and in the nearby 311 Tank Farm.  The 303‑F Building, also nearby, served as the pumping station for the various liquid and slurry waste transfers in the WATS process.  During most of the years of WATS operation (1975 to 1988) the tanks in the 334‑A Building received approximately 210,000 gallons (794 936.492 liters) of waste acids per year.[xx]

 

          The waste acids treated in the WATS operation included nitric, sulfuric, hydrofluoric, and chromic‑nitric‑sulfuric acids bearing uranium, Zircaloy‑2 components, copper, beryllium, and other fuel fabrication materials.  Waste acids were collected in the 334‑A Building tanks and then pumped to the 313 Building for neutralization with sodium hydroxide.  Wastes containing recoverable amounts of uranium were routed directly from the 333 Building to the 313 Building and were not treated as part of the WATS process.  Waste acids containing nonrecoverable amounts of uranium were pumped to the 313 Building for neutralization and, beginning in 1985, were centrifuged to remove solids.  Solids from the centrifuge were placed in drums and transferred to the 303‑K Radioactive Mixed Waste Storage Facility or to the Central Waste Complex in Hanford's 200 West Area for eventual disposal.  Filter press effluent and centrifuge effluent from 313 Building operations then was pumped to the 311 Tank Farm for storage and transported to Hanford's 100-H Area for evaporation.  Beginning in 1985, some neutralized waste effluents from the 333 Building were shipped from to Hanford's 340 Retention and Neutralization Complex for transshipment to the 200 Areas or offsite for disposal.[xxi]

 

 


 

                                    2.0  IRRADIATION PROCESSING AT THE HANFORD SITE

 

 

2.1  HANFORD'S SINGLE PASS REACTORS

 

          Nine plutonium production reactors, now closed and silent, cluster along a 14-mile (22.53 kilometers) stretch of the Hanford shoreline of the Columbia River.  Eight of these reactors, all except the N Reactor, are known as "single-pass" reactors due to the once-through nature of their light water cooling systems.  Known as "piles" in the 1940s, these machines drew cooling water from the river, and pumped it through a series of filtration, chemical treatment, and storage buildings and tanks.  The water then was passed directly through long, horizontal tubes in the reactors, where the solid, Al-Si-jacketed uranium fuel rods underwent active neutron bombardment.  From there, the water was pumped out the back of the piles, left for a brief time (30 minutes to 6 hours) in retention basins to allow for short-term radioactive decay, and then returned to the Columbia River.[xxii]

 

 

2.1.1  Historic Significance of B-Reactor

 

          Hanford's original reactor, B, was the first such full-scale nuclear facility to operate in world history.  Built by the Army Corps of Engineers and the DuPont Corporation in just 11 months between October 1943 and September 1944, it now is listed on the National Register of Historic Places.  B Reactor also has received special awards from the American Society of Mechanical Engineers and the American Society of Civil Engineers.

 

 

2.1.2  Single-Pass Reactor Buildings

 

          The next seven reactors, D, F, H, DR, C, KE, and KW (in order of construction) were similar in most features.  Built between 1943 and 1955, and shut down between 1964 and 1971, they had an average life span of just 21 years.  The construction and general specifications of B, D and F Piles (the original three reactors built in World War II) were similar to those of most of Hanford's other single-pass reactors, although C, KE and KW were slightly larger and contained some special features.  All of the piles rested on thick concrete foundations topped with cast iron blocks.  The reactor buildings themselves were reinforced concrete structures shaped like tiered wedding cakes with no containment domes.  They sat near the centers of five separate reactor areas of approximately 700 acres (283.28 ha) each.

 

          The core of each reactor was a series of graphite blocks that fitted together.  In the oldest six reactors, the cores each measured 28 feet (8.53 meters) from front to rear, 36 feet (10.97 meters) from side to side, and 36 feet (10.97 meters) from top to bottom.  In the K-Reactors, the cores each were 33 feet (10.06 meters) from front to rear, 40 feet from side to side, and 40 feet (12.19 meters) from top to bottom.  The graphite served as the "moderator" to slow and absorb extraneous neutrons from the basic nuclear chain reaction.  Each stack was pierced front to rear by aluminum process channels that held the fuel elements.  The first six Hanford reactors each contained 2,004 process channels, and the KE and KW Reactors each contained 3,220.  The "lattice," or pattern of process channel configuration was a simple rectangle, with only the corners of the core bearing no penetrations. Each reactor's graphite core was surrounded by thick thermal and biological shields.  The core and shields formed the reactor "block," and each block was enclosed in a welded steel box that functioned to confine a gas atmosphere.  The atmosphere of the earliest reactors was composed of helium, an inert gas selected for its high heat removal capacity.[xxiii]

 

          At the front and rear of each process channel, a carbon steel exit and entry sleeve known as a "gunbarrel" penetrated the pile shields.  The ends of each process tube flared into flanges to facilitate a close fit and interface against the gunbarrels.  Asbestos gaskets lay between the flanges and the stainless steel nozzles that projected from the front and rear of each process tube.  The nozzles connected to coiled lengths of aluminum tubing known as "pigtails" (originally one-half inch (1.27 centimeters) in diameter but later larger), which in turn connected to stainless steel crossheaders.  Devices known as "Parker fittings"a connected the pigtails to the crossheaders.  The crossheaders [originally 39 sections of four-inch- (10.16‑centimeter‑) diameter pipes] served to break down the huge water supply entering the reactor building's valve pit via two 36-inch- (91.44‑centimeters‑) diameter headers, then two 36-inch (91.44 centimeters) risers.[xxiv]

 

          Test holes extended from the right side of each Hanford pile for the irradiation of experiments and special samples.  Horizontal channels for control rods (HCRs) entered from the left side of each reactor, and vertical channels for safety rods (VSRs) entered from the top.  The control and safety systems functioned simply to absorb neutrons, thus slowing and eventually stopping the controlled chain reaction of neutron exchange between the uranium fuel elements.

 

          The early Hanford reactors also were equipped with various safety and control instruments that measured temperature, pressure, moisture, neutron fluxb and (radio)activity levels in the byproducts of the fission reaction.  Because no one instrument had enough range to measure neutron flux all the way from shutdown (background) levels to the approximately 1,000,000,000,000 (1 trillion) times background levels experienced during operations, each reactor was fitted with sub-critical, mid-range and full power flux instrumentation.[xxv]

 

 

2.1.3  Operation of the Single-Pass Reactors

 

          During actual operations, raw water was pumped from the Columbia River by pumphouses (known as 181 Buildings) located at and partially in the river.  From there, water for the earliest reactors was pumped to the 182 Buildings, which routed much of the water to the 183 Buildings for chemical treatment, settling, flocculation and filtration.  A small portion of the water proceeded directly from the 182 Buildings through large concrete pipes to the Hanford's 200 Areas [located 6 to 8 miles (9.66 to 12.87 kilometers) away] for treatment and use there in chemical separations and other operations.  From the 183 Buildings, Hanford's reactor process water was pumped to the 190 Buildings and stored in huge "clearwells" ready for pile use.  In the 190 buildings, sodium dichromate was added to the water to prevent corrosion of pile process tubes.  The 190 Buildings then supplied the reactors themselves as needed.  Some of the earliest HEW reactor influent systems also contained 185 Buildings for dearation, and 186 Buildings for refrigeration of coolant water.  However, these functions were found to be unnecessary and the 185 and 186 Buildings were diverted to other uses.

 

          At HEW's earliest reactors, each process tube usually was charged with 32 U fuel elements, along with a few dummy slugs in various configurations (either solid or perforated and hollow) at each end of the process channel.  Many fuel configurations could be used to achieve various desired flux patterns across the reactor lattice.

 

 

2.1.4  Change and Experimentation in Production Process

 

          The history of Hanford's single-pass reactor operations is one of constant change and experimentation.  Many questions puzzled and intrigued early Hanford scientists.  For example, they worried about the possibility of "slug failures," or the accidental penetration by cooling water of the aluminum jackets surrounding the fuel elements.  They knew that such penetration would cause the uranium to swell, thus blocking the coolant flow within the process tube.  This condition would necessitate tube removal and replacement, and could melt the fuel elements in that tube.  Also, fuel ruptures would allow the escape of radioactive fission products in larger than average amounts.[xxvi]           

 

          Another topic that intrigued the early operators of Hanford's reactors was that of temperature and neutron flux distribution.  At first, "poisons" (neutron absorbing materials) were distributed in a uniform pattern throughout the reactor core during operation.  This method of control produced a flux pattern that resembled a cosine (or bell) curve, front to rear within the pile.  Such a curve meant that while uranium elements in the center of the reactor achieved maximum or optimum irradiation, many of the fuel elements located in the rest of the reactor achieved sub-optimal irradiation, due to lower neutron flux.  This situation not only was inefficient in terms of utilization of the uranium supply, it also contributed to temperature gradients that caused expansion in the graphite in the central portions of the pile.

 

          Shortly after World War II, Hanford scientists tested several new poison patterns, with the goal of "flattening" the pronounced cosine curve, thus evening out the distribution of neutron activity and enlarging the area of maximum flux and temperature within the reactor.  Quickly, they learned that many alterations in poison distribution (control rod positions) would achieve higher and lower temperatures and exposures in various reactor zones.  They dubbed all of these manipulations "dimpling" the reactor.[xxvii]

 

 

2.1.5  Graphite Expansion Early Problem

 

          Of all the operational questions and issues that were pioneered in the Hanford reactors, almost none proved more compelling than those involving the graphite.  Swelling (expansion) of the graphite, along with embrittlement, was a side-effect of irradiation.  By late 1945, graphite expansion was causing the process tubes to bow, "binding" them too tightly with their fittings and other components, and straining the seals at the top and side corners of the reactor shields.

 

          As a result, a Graphite Expansion Committee was formed at Hanford in early 1946.[xxviii]  Ultimately, concern over the graphite expansion problem and its intrinsic threat to pile "life" led to the decision on March 15, 1946, to shut down B Reactor.[xxix]  However, in mid-1947, convinced by positive developments in graphite study, site managers made the decision to restart the reactor the following year.[xxx]

 

          By 1950, further experiments had made it clear that the addition of carbon dioxide (CO2) to the helium in reactor gas atmospheres could alleviate much of the graphite swelling problem.  The CO2, because it had a lower heat removal capacity than the helium, allowed the carbon atoms in the graphite crystal, displaced by irradiation, to heat up, become active, and hence realign themselves.  By 1954, the CO2 additions were working so well the oldest reactors operated with a gas atmosphere composed of 40% helium and 60% CO2, and tests were being planned to try even higher proportions of CO2.[xxxi]

 

 

2.1.6  Increased Power Levels/Production

 

          Beyond even the graphite puzzle however, no early (and ongoing) operational issue was more important to the Hanford Works than that of increasing the power levels.  B Reactor, along with D, F, and DR, was designed to operate at 250 megawatts (MW - thermal), while H, built five years later, was designed for 400 MW.  C Reactor, built during 1951-52, was designed for 650 MW, but the learning curve in pile operations took such a leap that the twin K Reactors (KE and KW) were built during 1953-55 designed for 1,800 MW each.[xxxii]

 

          Questions concerning how to achieve higher power levels, with consequent increases in plutonium production, had intrigued Hanford scientists since World War II.  In April 1949, an incremental test program that would take D‑Reactor to 330 MW was undertaken.  By January 1950, this experiment was so successful that DR-Reactor was being operated at 400 MW.[xxxiii]  With the acceleration of the Cold War, increased power levels in the Hanford reactors became even more important to perceived national defense needs.  From the late 1940s through the closure of the last single-pass reactor in 1971, pile history at Hanford was dominated by constant efforts to achieve increased power levels.

 

          By late 1956, under President Eisenhower's policy of "massive retaliation" and the boisterous challenges of Soviet Premier Kruschchev, the World War II power levels at the three oldest reactors had more than tripled, and stood at 800 MW.  At that time, a thorough set of modifications designed to allow increased coolant flow was completed at these reactors.  Similar modifications were made at the other single-pass reactors through the early 1960s, spurred by the threat of Soviet technical superiority as demonstrated by Sputnik.  As a result of these changes, and of fuel and tube design improvements, power level increases in the World War II reactors reached the 2,200 - 2,400 MW range by the mid-1960s, just after the Cuban "missile crisis" had once again boosted American desired for a strong nuclear defense.  The mid-1960s operating figures in the HW reactors were nearly 10 times the original design levels.  At the KE and KW Reactors, final operating levels in 1970 and 1971 stood at approximately 4,100 MW each.[xxxiv]

 

          Higher power levels themselves were easy to achieve, simply by adding enriched uranium fuel elements (those containing higher percentages of U-235).  However, increased power levels presented many puzzling operational challenges in the effects they imposed on reactor systems and components.[xxxv]  By mid-1951, Hanford scientists knew that the higher temperatures associated with increased power levels could produce substantially higher fuel jacketing and tube corrosion rates (and failure rates).[xxxvi]  However, their main concerns centered around how to deliver additional cooling water to, through, and out of the reactors.  Such water would be needed to offset "boiling disease," the Hanford term for a situation wherein steam might form in a process tube.  If this happened at higher power levels, greater water pressures would be needed to sweep the steam from the tube (and thus to prevent a localized meltdown).[xxxvii]

 

 

2.1.7  Operating Challenges at Higher Power Levels

 

          By mid-1953, effluent removal piping at the oldest reactors, already operating at 20% to 50% above design capacity, was under intense study.[xxxviii]  At the same time, operators realized that the filtration capacity for intake water would have to be increased well beyond the original capacity of approximately 35,000 gallons (132 489.42 liters) per minute (gpm) per reactor.  More important, however, was the need to increase the intake pumping capacity.[xxxix]

 

          In the meantime, as power levels crept upward in the oldest reactors during the late 1940's and early 1950's, fuel element ruptures became a reality.  The first rupture occurred at F Reactor in May 1948, and two others occurred later that year at B Reactor.[xl]  The number of fuel element rupture incidents increased slowly during 1949-1950, but expanded dramatically in 1951 when Hanford Works experienced 115 fuel failures.[xli]  This number continued to climb throughout the early 1950s, bringing further focus to fuel fabrication improvement studies.

 

          Along with fuel element failures, higher power levels and higher temperatures brought increasing levels of corrosion and failure of process tubes.  By 1953, each Hanford reactor needed an average of 200 tube replacements per year.[xlii]  In order to reduce the ruinous corrosion, a special "Flow Laboratory" was built in late 1951 in a modified WWII refrigeration building.  It functioned to study corrosion and heat transfer within process tube "mock-ups" (simulations).[xliii]

 

          At the same time, the Hanford Works began an intense review of intake water treatments.[xliv]  Sodium dichromate, a key corrosion inhibitor that had been added to reactor water since World War II, was evaluated closely.  Because sodium dichromate was known to have detrimental effects on the fish of the Columbia River, much experimentation with other corrosion blockers was undertaken.[xlv]  However, due to dramatic rises in tube and fuel element corrosion when the sodium dichromate was withdrawn, site scientists decided to continue using it.[xlvi]

 

          The drive to higher and higher power levels in Hanford's reactors throughout the late 1940's and mid-1950's was accompanied by the need for several changes to enhance operating safety.  The "last ditch" safety system in the five oldest reactors was replaced with tiny, neutron-absorbing, nickel-plated carbon steel balls.  These balls were poised in hoppers at the top of the piles, ready to pour in and tamp down the fission reaction if necessary.[xlvii]  Physical braces and supports, and many additional instruments also were added.[xlviii]

 

          Other changes in reactor operations shortened the time required to perform routine operating chores.  Since World War II, charge-discharge ("C-D") operations (loading and unloading the fuel elements from a reactor) were performed while a reactor was shut down.  However, by 1950 experiments were underway to perform C-D operations while a reactor was running.[xlix]  During the early and mid-1950s, such a system was tested successfully.  It operated remotely, and worked by flushing fuel elements down the process tubes via high pressure water.[l]  Due to cost, this system were not installed at the oldest five reactors, but it was emplaced in the other, newer reactors.

 

          Another change aimed at saving shutdown time in the Hanford reactors concerned "purging" or cleansing the process tubes.  Minerals, elements and suspended solids in the Columbia River's water routinely built up a film on the process tube surfaces.  This situation caused heat build-up within the reactors.[li]  Since World War II, operators had "purged" (scrubbed) the film from the tubes on a monthly basis, while the reactors were shut down.[lii]  However, by the early 1950's the Hanford Works was trying to conduct "hot" purges -- so called because they occurred while the reactors were running.  Such operations were very effective in removing reactor films, but greatly increased the levels of pollution entering the Columbia River.[liii]

 

          To help ameliorate the high levels of radioactivity, restrictions were placed on the frequency of purges that could be conducted during autumn periods of low river flow.  Also, a series of experiments was initiated to find ways to protect the river.[liv]

 

 

2.1.8  Reactor Upgrades for Increased Production

 

          Beginning in 1954 and continuing into the early 1960s, a series of major modification projects designed to strengthen the reactor systems necessary to support power level increases were emplaced at the eight single-pass Hanford piles.  Designated "Reactor Plant Modifications for Increased Production," these projects substantially increased intake pumping, filtration, and chemical treatment and storage capacities.[lv]  Effluent systems likewise were strengthened and enlarged dramatically.[lvi]  Instrumentation with higher range capacity was emplaced.[lvii]  Electrical upgrades and many other miscellaneous changes were made within reactor systems.  One such modification was the removal of aluminum liners (known as "thimbles" by Hanford workers) in some of the process channels, because higher operating temperatures would cause these liners to melt.[lviii]

 

          Ironically, just as these projects were underway, significant changes in fuel elements and process tube designs and materials took place at the Hanford Works.  These developments allowed dramatic increases in reactor power levels, once again straining the newly upgraded support systems.  Much of the increase in power level was made possible by the use of the I&E fuel elements, which were first tested on a production basis in 1958.[lix]  Other operating efficiencies that came quickly in the late 1950's and early 1960's resulted from the gradual replacement of aluminum process tubes with tubes made of Zircaloy-2.  Also, self-supported (projection, bumper or ribbed) fuel elements were developed at Hanford.  Such fuel elements allowed greater passage of cooling water, again allowing higher power levels to be sought within a margin of safety.[lx]

 

2.1.8.1  Maintenance and Safety Issues at Single-Pass Reactors.  The higher power levels permitted by the development of internally and externally cooled fuel elements, ribbed fuel elements, and new process tubes, brought multiple operating challenges to the support systems of the Hanford reactors.  Pumps and pipes developed destabilizing leaks, while electrical capacities proved inadequate.  Much of the reactor instrumentation also was rendered obsolete.  Even the graphite swelling problem increased, as the levels of neutron flux and bombardment rose exponentially.[lxi]  Safety reviews called for a mounting list of improvement projects.[lxii]

 

          From that time forward, the story of the Hanford single-pass reactors became one of how to design and fund all of the support systems upgrades that were needed.  One project that was accomplished at all of these reactors during 1960-62 was the construction of a large exhaust gas confinement system.  It was comprised of a below-ground filter building, duct work that routed gases from the reactor through these filters and then back into the exhaust stack, and sampling equipment.  Another part of this project provided a rear face fog spray system for each reactor, and a front face fog spray system at C, KE and KW Reactors.[lxiii]  Additionally, the Ball-3X systems at most of the reactors were upgraded in the early 1960s, as part of an overall "exposure reduction program" undertaken by Hanford's Irradiation Processing Department.[lxiv]  Several instrumentation improvements and replacements also were approved for many of the reactors, based on safety and control considerations.[lxv]

 

 

2.1.9  End of Single-Pass Operations

 

          In January 1964, President Lyndon Johnson announced that, due to a decreased need for special nuclear material (SNM), Hanford's reactors would be shut down in a phased sequence beginning in December 1964.[lxvi]  At the same time, Columbia River pollution from reactor effluent was becoming an increasingly important factor in regional and national considerations.  Hanford scientists, as well as health officials in Washington, Oregon and the U.S. Public Health Service became more and more concerned with the effects of reactor effluent in the huge river.  By 1960, the total volume flow from the Hanford reactors had increased approximately ten-fold over that of the World War II period, shortening the practical retention time to only about 30 minutes and making diversion of unusual effluents to "cribs" (percolating areas dug into the earth) or other holding areas virtually impossible.  Furthermore, the total amount of radioactivity reaching the Columbia River stood at nearly 14,000 curies per day.[lxvii]

 

          Within this effluent flow, the main isotopes of concern were phosphorus 32 (P-32), zinc 65 (Zn-65), chromium 51 (Cr-51), iron 59 (Fe-59), and arsenic 76 (As-76).  It had been known since the late 1940s that these isotopes  concentrated within aquatic plants and animals to vastly higher levels than were found in the river water itself.  Multiple studies pointed to the fact that the Columbia's water could be at or below permissible levels for various radionuclides, and still present a hazard to consumers of river fish, ducks and other wildlife.[lxviii]

 

          Throughout the late 1950s and early 1960s, virtually every aspect of the bioaquatic and potential downstream health consequences of reactor effluent was examined, including the effects of temperature, operating purges, various purge agents and filtration aids, fuel element ruptures, sodium dichromate, and the radionuclides themselves.[lxix]  Various solutions were proposed and tested.  Salient among these was the concept of passing reactor effluent through beds of aluminum shavings, in order to entrap various radionuclides.[lxx]  Laboratory tests seemed promising, but a production-size bed installed in 1960 at the D Reactor retention basin demonstrated so many shortcomings that the idea of decontamination of reactor effluent via aluminum test beds was effectively abandoned in 1961.[lxxi]

 

          Another concept that was explored thoroughly at Hanford was that of varying the intake water treatments.  However, mixed results, combined with undesirable side effects, resulted in very little practical improvements.[lxxii]  In the early 1960s, an idea that had been explored in the 1950s for reducing radionuclide releases to the Columbia River was revived.  This "Inland Lake" concept proposed routing reactor effluent through trenches to artificial, inland lakes dug in the center of the site where the distance between land surface and the underground water table was significantly greater than it was near the reactor retention basins.  Proponents of the idea pointed to the longer time period for radioactive decay and thermal cooling of effluent, before the wastes finally would reach the river.  However, studies conducted in the 1950s had demonstrated undesirable effects, including the wind entrainment of radioactive mists that could spread contamination over wide areas extending even to offsite.  Furthermore, problematic underground mounds in the water table, caused by disposal of low-level liquids wastes from chemical processing plants near the center of the site would be worsened by the addition of reactor effluent.[lxxiii]

 

          As the reactor shutdowns began at Hanford in the mid-1960's, operators and scientists struggled to extend the viability of the remaining piles by developing environmentally acceptable means of effluent disposal.  In the spring of 1967, with five single-pass reactors operating, a Hanford summary report on alternate methods of reactor effluent treatment and disposal listed several additional options.  Conversion to recirculating cooling systems was listed as economically prohibitive, since it would involve providing 400,000 gallons (1 514 164.75 liters) per minute of additional cooling (pumping) capacity per reactor, with all attendant piping modifications.  Other related equipment also would be needed for each reactor, for a total conversion cost of $32 million per reactor.  Other potential solutions also were expensive and posed awkward siting problems between the reactors and the Columbia River.  Still other, less expensive proposals each came with physical or acceptability barriers.[lxxiv]  The eight single pass reactors at the Hanford Site all closed permanently between December 1964 and January 1971.

 

 

2.2  N REACTOR OPERATIONS

 

          The Hanford Site's ninth defense production facility, N Reactor, operated from early 1964 to December 1986.  Like Hanford's single-pass reactors, N Reactor was tied in umbilical fashion to the Columbia River, and it was light water cooled, graphite moderated, and fueled with bored metal uranium.  Also, none of the defense production reactors at the Hanford Site were equipped with containment domes.  Nevertheless, there were major differences between N Reactor and the older Hanford piles.  N Reactor recirculated its primary coolant water, instead of returning it to the river, thus releasing significantly less radioactive effluent (waste water) on an everyday basis.  Additionally, the light water coolant circulated under pressure, allowing for much higher operating temperatures, and the water was demineralized so that less film was deposited inside the process channels.

 

          Another major difference between N Reactor and the older Hanford piles was that N Reactor had a negative-void coefficient design, while the single pass reactors had a positive-void coefficient design.  The negative-void factor was a crucial safety feature because it meant that when a steam bubble or void developed in a process tube, the effect tended to shut down N Reactor.  This factor prevailed because, at N Reactor, there was a low ratio of graphite moderator to U fuel.  The cooling water provided a significant portion of the moderating effect.  Thus, loss of coolant had the effect of reducing reactivity.  In the single pass reactors, a steam bubble or void tended to increases the neutron flux logarithmically, thus enhancing the chances for a nuclear accident.  Lastly, in 1966, the steam generated from the heat of the nuclear chain reaction was captured at N Reactor to produce electricity for the domestic power needs of the Pacific Northwest.  Today, N Reactor remains as the only U.S. defense reactor that served a "dual purpose."[lxxv]

 

 

2.2.1  105 N Building and Reactor

 

          The 105-N (N Reactor) Building was a reinforced concrete structure sitting atop a thick slab of reinforced concrete.  The reactor core itself was 39 feet (11.89 meters), 5 inches (12.70 centimeters) high, 33 feet (10.06 meters) wide, and 33 feet (10.06 meters), 4.5 inches (11.43 centimeters) tall.  It consisted of 1,800 tons of nuclear grade graphite blocks notched, interlaid and pierced by 1.004 process channels.  The lattice was arranged in a rectangle 32 feet (9.75 meters) high by 34 feet (10.36 meters) wide, with 21 channels omitted from each corner.  Eighty seven HCRs entered the N Reactor core, 41 from the left side and 46 from the right side.  One hundred and eight vertical safety channels existed to receive ceramic "3X" balls to shut down the reactor in case of need.  A small number of other channels pierced the core to hold experiments, and to position traverses to measure graphite distortion over time, graphite temperature, and flux.  Graphite bowing over time was both expected and feared by the designers of N Reactor.  The original reactor manual stated that "there is as yet no determination of the maximum extent to which contraction of nuclear graphite can be induced by irradiation."  An 8.3-inch (21.08 centimeters) depression at the top center of the graphite moderator was chosen as the original design basis, corresponding to about a three percent contraction, while 12 inches (30.48 centimeters) was "estimated to be tolerable for the reactor as built."  The design lifetime of the reactor was 25 years.[lxxvi]

 

          The N Reactor core was surrounded special layers of reflector graphite, then by water cooled thermal shields constructed of boron steel and cast iron, and then surrounded again by a primary shield of high density concrete.  Helium gas formed the pile atmosphere.  A fog spray system at both the front and rear reactor faces was provided for contamination control and cooling in case of a loss of contaminated steam from the core.  The water influent system began at the 181-N River Pump House, proceeded to the 182‑N High Lift Pump House where raw river water was treated and where demineralized and deoxygenated water was injected into the makeup and cooling water, the 183‑N flocculation and filter plant, and to the 183-NA Pump House that sent coolant water into the reactor.  Extra supplies of treated water were held in the 183-NB clearwell.  N Reactor's primary coolant system used from 100 to 1,500 gallons (378.54 to 5 678.12 liters) per minute of fresh, treated water, a vast decrease from the 35,000 to 105,000 gallons (132 489.42 to 397 468.25 liters) per minute consumed by Hanford's single pass reactors.[lxxvii]

 

 

2.2.2  N Reactor Operating Changes and Challenges

 

          Over its years of operation, many changes took place at N Reactor.  From 1965-67, a "co‑product" demonstration campaign took place, in which tritium was produced in the reactor from special lithium aluminate fuel elements.  Beginning in 1966, N Reactor steam for electrical production was harnessed at the Hanford Generation Plant (HGP) constructed just west of the pile by the Washington Public Power Supply System (WPPSS).  In 1971, N Reactor was ordered closed due to a diminished national need for defense plutonium production.  An agreement was reached to keep the reactor running primarily for electrical production.  During the 1970s, a time when the entire Hanford Site undertook modifications to achieve more desirable interfaces with the environment, a number of upgrades to N Reactor's waste treatment systems were emplaced.  Trenches were dug to receive reactor effluent, thus allowing a longer percolation time through the soils just inland from the reactor, for radioactive decay to occur before effluents reached the Columbia River.  Monitoring instrumentation for waste products was added, secondary and shield coolant loops were converted from single-pass to recirculating systems, and a special containment tank was constructed to hold the pile purge effluent for transfer to Hanford's high level waste storage tanks.  Release of this purge material to the Columbia River was discontinued.[lxxviii]

         

          Beginning in the early 1980s, a large defense build-up was ordered by President Ronald Reagan.  At the same time, N Reactor arrived at 20 years old and began to experience system failures of many types.  One fundamental problem was the distortion of the graphite stack, where built-in slip joints could not accommodate all of the local distortion, some block cleavage, and actual separation of blocks that had occurred within the central core.  Such distortions produced "significant changing problems" by 1982.  Additionally, the 1982 summer outage revealed center transverse contraction resulting in a total sag of about three inches, and tube elongation to the extent that many connector clearances were rated as "minimal."  As N Reactor struggled to remain a crucial piece of America's defense arsenal, many system upgrades were undertaken.  In the 189/190‑D Thermal Hydraulics Laboratory, a complete mock-up of N Reactor's core, in it's actual distorted and curved condition, was built, in order to study remediation concepts.  An N Reactor Loop Components Test Facility, a high temperature, pressurized, recirculating demineralized water test loop also was constructed to model and evaluate leaks in the primary flush lines of the core, various valves, and alternative ideas for operations.  Another model was built to test inspection and removal equipment for the graphite cooling tubes, and to demonstrate a process tube drying system.  In April 1986, an accident at the Chernobyl nuclear plant in Soviet Russia brought about a stand down for safety evaluations at N Reactor.  The reactor never re-opened.  It was ordered to cold standby by the DOE in February 1988, and a large D&D project leading to final disposition began in 1994.[lxxix]

 

 


 

                                        3.0  SPENT FUEL HANDLING AT THE HANFORD SITE

 

 

3.1  ORIGINAL LAG STORAGE PRACTICES

 

          After irradiation in a reactor, nuclear fuel is known as "spent fuel."  In defense production at the Hanford Site, this fuel has always placed under water, allowed to undergo a period of radioactive decay, and then chemically dissolved and "re-processed" to separate the Pu product from associated fission products and other elements.  In HEW jargon, the solid U fuel elements were known as "lags" as soon as they became spent fuel.  B‑Reactor and HEW's other earliest reactors were constructed with spent fuel basins just below the rear faces.  The fuel was literally pushed out the rear face of each reactor by charging fresh fuel into the front.  Spent fuel basins at the earliest Hanford reactors each were 81 feet (24.69 meters) by 68 feet (20.73 meters), and were divided into two sections each.  The basins were 20 feet (6.10 m) deep, although the water was maintained at about 16 feet (4.88 m) deep.  Each basin was served by submerged buckets that were suspended from a monorail via 25‑foot (7.62‑meter) yokes.  Long rakes and tongs were used to load each bucket with one-half ton of fuel elements.

 

          Viewing of the discharge area was accomplished with two main periscopes, located on the ceiling of the discharge area and on the wall opposite the rear face of the pile.  Additionally, the latter location contained a "Fly-eye" viewer that consisted of four wide-angle lenses.  A shielded cab, which could be attached to the 50,000‑pound (22 679.62 kilograms), 8 to 10 feet (2.44 to 3.05 meters) wide "D" elevator, also had its own periscope.  One last periscope was located in the labyrinth that led to the discharge area balconies, but its view often was blocked by the "D" elevator (which had to be raised to the top of the reactor's rear face during discharge operations).  Thermocouples were placed at the inlet and outlet of the storage basin, and water temperature levels as indicators of radiation intensity were monitored carefully.

 

          The earliest spent fuel handling practice at the Hanford Site was to keep the lags in the basins at the reactor rear faces for a very short period of time (several hours to one day).  The irradiated fuel rods then were loaded into shielded rail cask cars and taken to the 200‑North Area for storage in the 212 Lag Storage Buildings.  Within any one of these three buildings, the rods were stored for periods of time ranging from a few weeks up to perhaps as long as 50 days, to allow for isotope decay, before they were taken to either T‑Plant or B‑Plant for chemical separation.[lxxx]

 

 

3.2  212 LAG STORAGE BUILDINGS CLOSE

 

          As the needs of the Cold War rapidly increased Pu-239 production at Hanford, difficulties developed with the 212 Buildings.  By 1950, Site planners realized that additional capacity for lag storage was needed.  One key factor was the AEC's decision to store spent fuel from 90-125 days before re-processing, in order to reduce the emissions of iodine 131 (I-131) and other gaseous fission products into the regional environs.  Other crucial factors included the increased amounts of fuel being produced and handled once the H and DR reactors came on line in 1949 and 1950 respectively, and the anticipation that various forms of E-metal would be tried in order to push production even higher.  In 1951, with C-Reactor under construction, as well as the desire to save the transportation costs to and from the 212 Buildings and to reduce radiation exposure to workers from fuel transfers, the 212 Buildings closed.  From that time forward, spent fuel at Hanford was stored only in the fuel basins at the rear faces of the reactors.[lxxxi]

 

          The reactor fuel storage basins, as had the 212 Buildings, operated within certain fundamental parameters.  All cooling was accomplished using either once-through or feed-and-bleed principles.  Filtered water was routinely added to the basins and water was discharged either via overflow weirs or floor drains.  The discharged water was routed to cribs for soil filtration.  As a result of this routine water addition, the fuel storage basins at Hanford were relatively clean radiologically.  Additionally, fuel was always stored in open containers.  This facilitated heat removal after discharge from the reactor.  Corrosion products were not an issue because following a relatively short storage time, fuel was processed.  The fuel storage basins at the KE and KW reactors operated in the same manner, although they were larger.  At these piles, the rectangular, reinforced concrete basins each were 125 feet (38.10 meters) long, 67 feet (20.42 meters) wide, 21 feet (6.40 meters) deep, and were divided into three sections.  By the early 1960, lag storage time at HW had increased to an average of 200-250 days.[lxxxii]

 

 

3.3  CLOSURE/RE-OPENING OF FUEL STORAGE BASINS

 

          As each HW reactor closed between 1964 and 1970, its spent fuel basin likewise closed.  In some cases, fuel storage basins at a given reactor would remain open a number of months after the pile itself had shut down, in order to accommodate fuel from another reactor.  However, all lag storage basins except for the N Reactor basin closed by 1971.  In 1972, the last radiochemical processing plant at the Hanford Site, the PUREX (plutonium uranium extraction) Plant entered a long shutdown period (although it later re-opened).  The N Reactor, because of its dual-purpose design, was kept operational to support Pacific Northwest electrical power needs.  N Reactor was operated in this mode throughout the decade, and continued to produce spent fuel.  The N Reactor fuel storage basin was not sized to support the resultant fuel inventories.  As a result, the decision was made to use the K Reactor spent fuel basins for additional storage space for N Reactor lags.

 

          The K East basin was the first to be modified to store N Reactor fuel.  It received only superficial cleaning, and the bare concrete walls of the basin were left uncoated.  All drains and overflow weirs were blocked off and a water recirculation system was installed.  The recirculation system consisted of two pumps, two underwater cartridge filters for particulate removal, and two water-to-water heat exchangers for basin cooling.  Storage racks were installed on the basin floor to support single tier storage of N Reactor fuel.  Filtered water was used to supply the basin water make-up needs.  A barrier was installed across the entrance to the North Loadout Pit to isolate it from the basin proper.  The actual construction activities were completed and the facility began accepting N Reactor fuel in 1975.  N Reactor fuel was shipped and stored in open containers.  The containers (canisters) were specifically designed for this purpose.  These canisters remained unchanged from the design used to support earlier N Reactor operational needs.

 

          The fuel inventory quickly grew in the K East basin and along with it, radiological problems.  With the basin sealed and with no ability to add clean water and discharge contaminated water, fuel corrosion products were captive in the facility.  Radioactive contamination and radiation exposure levels increased.  Steps were taken to mitigate this situation included the addition of a skimmer system along with a sand filter, and later, an ion exchange system.  As the PUREX Plant remained closed and N Reactor continued to operate, plans were initiated to modify the K West basin to accommodate the extra fuel.[lxxxiii]

 

          The K West modification was designed to prevent a recurrence of the K East Basin experience.  The K West Basin was drained and the walls and floor were cleaned and sealed with an epoxy material.  The drains and overflow weirs were blocked off.  All of the basin clean-up systems in operation at K East were installed in the K West Basin.  These included a basin recirculation system with cartridge filters and heat exchangers, a skimmer system with a sand filter, and an ion exchange system.  The decision was also made to fill the basin and maintain water level using demineralized water.  A lid design was developed for the existing fuel storage canisters which allowed them to be  closed.  The design allowed the canisters to vent if there was any gas generation.  Fuel shipments to the K West Basin began in 1981, with all fuel shipped to and stored in closed canisters.[lxxxiv]

 

          In 1983, when the PUREX plant was getting ready to resume reprocessing of spent fuel to recover plutonium and uranium, the fuel in the K East basin was sorted to separate the weapons-related fuel from that used to generate electricity.  The fuel was dumped from the canisters, sorted and placed back in the open canisters.  A proposal to place the K East fuel in sealed canisters, like those used in K West, was rejected.  Today, the K East Basin holds the nation's largest single concentration of stored spent fuel.  The existing fuel inventories include 3600+ open canisters of spent fuel stored in the K East Basin and 3800+ closed canisters of spent fuel stored in the K West Basin.  This inventory totals ~2100 MTUs.

 

 

                                       4.0  RADIOCHEMICAL SEPARATIONS PROCESSING

                                                             AT THE HANFORD SITE

 

 

4.1  THE BISMUTH-PHOSPHATE PROCESS

 

 

4.1.1  Start-up of Radiochemical Processing at HEW

 

          The earliest radiochemical processing operations at the Hanford Engineer Works using "hot" (irradiated uranium) feed began at the 221-T Cell Building, also known as T‑Plant or T-Canyon, on December 26, 1944.  This event was historic because T-Plant was the first full-size radiochemical processing plant in the world.  The only previous radiochemical processing of irradiated uranium fuel elements had been done on an experimental scale at a facility known as the Clinton Semi-Works (or SMX), located at the Clinton Engineer Works in Oak Ridge, TN.[lxxxv]

 

 

4.1.2  T, B, and U Process Groups

 

          The original separations process used at HEW was the bismuth-phosphate (BiPO4) process.  It was based on the principle that bismuth phosphate is similar in crystal structure to plutonium phosphate.  The entire operation was a batch, precipitation process that achieved separation by varying the valent state of plutonium 239 (Pu-239), and then by repeatedly dissolving and centrifuging plutonium-bearing solutions.  The steps of the bismuth-phosphate process were carried out first in T‑Plant, then in the 224-T Bulk Reduction Building, and then in the 231-Z Isolation Building.  A second and third set of facilities for both the first and second phases of the BiPO4 process also were built at HEW, but the final steps always took place in the 231-Z Building.  The second set of facilities was known as the B Process Group, and consisted of the 221-B (B-Plant) and 224‑B Buildings and their associated support structures.  B-Plant began processing irradiated U at Hanford on April 13, 1945.  The third set of facilities was known as the U Process Group, and consisted of the 221-I (U-Plant) and 224-U Buildings and their associated support facilities.  The U Process Group never handled irradiated uranium, but served as a training facility until another use for the buildings was developed in 1952.[lxxxvi]

 

 

4.1.3  Original Separations Buildings

 

          The 221-T Cell Building originally was 85 feet (25.91 meters) wide by 875.5 feet (266.85 meters) long by 102 feet high.  It was a dense, thick, reinforced concrete, rectangular mass, approximately one-quarter below grade, with no windows.  At the time that T-Plant was built, its design and construction was described by the DuPont Corporation builders as "extremely unusual...due to process requirements.  In other words, once the equipment in any of the cells is placed in operation, it will not be possible to approach it for maintenance or to manually remove or fit up piping."  Remote operational requirements, as well as radiation shielding requirements, resulted in the 221‑T Building being unique, and a first-of-a-kind structure in the world, when it was built.  The 221‑B Building was virtually identical to T-Plant, except that it had 65 feet (19.81 meters) less length and did not contain a special head-end testing laboratory that was included in T‑Plant.

 

          The foundation of each canyon building structure was a reinforced concrete pad varying from six to eight feet (1.83 to 2.44 meters) in thickness with a spread footing.  Outside building walls were likewise reinforced concrete three to five feet (0.91 to 1.52 meters) thick.  The barricade wall between the cells and canyon and the galleries was seven feet (2.13 meters) thick.  Each building had a suspended flat concrete roof varying from three to four feet (0.91 to 1.22 meters) in thickness.  Construction joints were provided between each building section and expansion joints at frequent intervals.  The inside surfaces of the cells and pipe trench, removable cover blocks, the deck floor level in each canyon, and each second floor control gallery were painted with "Amercoat,"a an epoxy-based contamination fixant sealant, to reduce the porosity of the concrete surfaces.

 

          Each 221 Building structure was separated into two main portions - Galleries and Canyon, with the inside of the building being divided into 22 sections (for T-Plant) and 20 sections (for B-Plant).  Each section encompassed two cells.  Sections were 40 feet (12.19 meters) long with the exception of Sections 1, 2, and 20, which were 44 feet (13.41 meters), 43 feet (13.11 meters), and 43.5 feet (13.26 meters) respectively.

 

          Inside the head-end of T-Plant, were two developmental equipment cells, A and B, having the same length as cells 1, 2, 3, and 4 [a total of 65 feet (19.81 meters) in length].  The essential difference between this testing laboratory and a standard T-Plant section was that each testing laboratory cell contained the equipment corresponding to that in two standard cell sections.  The head-end laboratory section also included a continuation of the basement, first and second floor galleries that ran the length of T-Plant.  However, these galleries turned at the head-end and continued across to the rear wall of the building.

 

 

4.1.4  Galleries

 

          The HEW canyon buildings were so designed that the control panel boards, chemical and service distribution, were located in three galleries, one above the other along the "front" side of the building; the west side in the case of T-Plant and the north side in the case of B-Plant.  The first gallery, at the basement level, was used principally for electrical distribution and control cabinets.  The first floor gallery consisted of a piping loft containing steam, water, air, and chemical headers as well as piping connections between the panel boards and weigh tanks on the second floor and through-wall cell piping.  The second floor gallery was the control center for the cell equipment, and was known as the operating gallery.  Each 40-foot building section constituted a separate unit, and were controlled by separate gauge boards in the operating gallery.  The gauge board panels were installed in a row along the barricade wall between the canyon and the galleries, with weigh tanks along both front and back walls of the gallery.

 

 

4.1.5  Canyon

 

          The lower portion of the canyon below the "deck" (ground) level contained 40 individual concrete cells having removable concrete cell-block covers.  The cell covers were constructed with overlapping, step-wise edges, to contain the radiation within the cells.  A 10-foot (3.05‑meter), 6‑inch (15.24‑centimeter) square exhaust duct ran along the back wall of the building paralleling the bottom of the cells and was connected by an underground concrete duct to the 291 Exhauster Buildings and Stacks for the removal of cell fumes.  Immediately above this duct was a pipe trench which also paralleled the cells, containing inter-connecting cell piping.  The pipe trench was also covered with removable, sectional concrete block covers.

 

          The construction of the cells was standardized as much as possible, to ease the maintenance problems as much as possible.  The sections having standard designs were 4, and 6 through 20.  Section 1 differed in that it was a large cell with two long openings for the immediate storage of partially precessed material.  Section 2 contained two long openings of the same size, one of which centered over the railroad track where irradiated fuel elements were brought into the building, and the other which housed initial cell equipment.  A reinforced concrete railroad tunnel, extending 150 feet from the front sides of the buildings provided rail service to this section.  Section 3 differed in that the pipe trench ended opposite cell #5.  Section 5 differed in that cell #10 was much deeper, because it served as a collection point for drainage to the sewer section.  At T-Plant, the head-end sections differed in that the pipe trench terminated in a manner that would allow for future extension of the building if desired.  (Such extension did not happen.) 

 

 

4.1.6  Processing Equipment

 

          The equipment installed in the cells consisted mainly of centrifuges and vessels with and without agitators, and connecting piping between cell walls and equipment.  Around the periphery of each cell were 42 flanged piping connections serving the cell equipment.  Special piping connectors were used allowing pipes, conduits, and instrument leads to be connected by tightening a single nut.  Vertical connectors were used for electrical connections only, and horizontal connectors were used for piping and instruments only.

 

          The canyon portion of each Cell Buildings was served by an overhead bridge crane equipped with 75-ton and 10-ton hooks as well as four independent monorail hoists of one and one/half-ton capacities.  The crane cab was designed to contain special controls, observation and communication facilities in order to remove cell blocks, cell equipment and cell piping by remote control.  The canyons also each contained a second overhead bridge crane, 10-ton capacity for maintenance use only, when the building was completely shut down.

 

 

4.1.7  Stair Towers

 

          Four-story reinforced concrete stair towers were constructed along the front side of each 221‑T Building (eight in T-Plant and seven in B-Plant) to provide access to the three gallery levels and the crane-cab runway.  These stair towers also housed heating and ventilating equipment and rest rooms for the galleries.  Reinforced concrete labyrinthed stair towers were built along the rear sides (east side in the case of T-Plant and south side in the case of B-Plant), to provide access to the canyon portion of each building at the deck level.  T-Plant had ten such rear stair towers and B-Plant had nine.[lxxxvii]

 

 

4.1.8  224 Bulk Reduction Buildings

 

          The 224 Buildings were constructed of reinforced concrete.  Each was a three-story frame structure with concrete and concrete block exterior and interior walls.  The front of each 224 Building was placed precisely 150 feet from the back of its corresponding 221 Building, and in line with the front of its process group's 222 Control Laboratory.  Each 224 Building contained a total of 21 rooms not including two stair towers, one closet, one janitor's closet, and an elevator "penthouse."  The overall dimensions were 60 feet (18.29 meters) 1 inch (2.54 centimeters) by 197 feet (60.05 meters) long, with a total area of 11,982 square feet (1 113.16 square meters).  Each building was 40 feet (12.19 meters) high for the majority of its length, but reached higher elevations over two stair towers and over the small penthouse area.

 

          The foundation of each 224 Building was comprised of reinforced concrete walls with spread footings, reinforced concrete piers and beams, and concrete pads.  Each floor slab was reinforced concrete 4 to 12 inches (10.16 to 30.48 centimeters) thick.  Each roof consisted of flat reinforced concrete 5 to 12 inches (12.70 to 30.48 centimeters) thick, covered with built-up felt, gravel surfaced roofing, and containing 8 wood frame ventilators with meters.  The roof slabs were removable, so as to allow the movement of large equipment pieces in and out.

 

          Each 224 Building was essentially divided into two main sections:  the process cell section, and the office and operating gallery section.  The back side of the main structure contained the process cells and had one foot thick concrete walls with a balcony running around three sides.  The 27-foot (8.23‑meter) by 197-foot (60.05‑meter) process cell area contained five cells known as Cells A to E inclusive.  These cells were served by a hand-operated overhead crane.  Cells A through D measured 27 feet (8.23 meters) by 28 feet (8.53 meters).  Cell F measured 25 feet (7.92 meters) by 51 feet (15.54 meters), was L‑shaped, and had an office in one corner of it.  A glass enclosure was located in the cell against this office wall, where the partially finished product was collected for transfer to the 231-Z Isolation Building.  In Cell C, the right-hand portion was a pit which connected with an underground pipe tunnel that ran from the center line of Sections 13 and 14 in the corresponding 221 Building to each 224 Building.

 

          The floors in the cells were sloped to a trench along the wall, for gravity delivery to waste collection tanks.  The walls and floors in Cells A through E, and walls, floors, and ceilings in F Cells and its office were painted with Amercoat.  A mezzanine floor extended across the side facing the corresponding 221 Building.  Gauge boards and weigh tanks used in connection with Cell F were mounted on this mezzanine.

 

          One-foot (0.30‑meter) thick interior walls divided the process cell section of each 224 Buildings from the office and gallery section.  The "front" (offices and gallery) side of the main structure was reinforced concrete frame with 8-inch (20.32‑centimeter) concrete block panels and 8-inch (20.32‑centimeter) and 4-inch (10.16‑centimeter) concrete block partitions.  An elevator was installed adjacent to the No. 1 stair tower and was provided with an outside concrete loading platform to facilitate the movement of chemicals to and from trucks.  The first floor contained offices, a chemical storage room, and other service rooms.  The second floor was principally a pipe loft containing five concrete vestibules opposite each centrifuge platform.  All chemical and service lines entered the building on this level.  The third floor was an operating gallery that contained gauge boards, tanks, and instruments.[lxxxviii]

 

 

4.1.9  231 Isolation Building

 

          The 231-Z Building was located in the western portion of the 200-West Area of the Hanford Site, midway between T-Plant and U-Plant.  Originally, this structure was a two-story, flat roofed, reinforced concrete, frame building with 8‑inch concrete block panels and 4‑inch (10.16‑centimeter) and 8‑inch (20.32 centimeter) concrete block partitions.  Overall dimensions were 147 feet (44.8 meters) by 189 feet (57.61 meters) 10‑inch (25.40 centimeters) by 24 feet (7.32 meters) 6‑inch (15.24 centimeters) tall, with a total of 27,964 square feet (2597.94 square meters).  A one-story ventilation and equipment room ran along the west end of the building.  The 231-Z facility had no windows.

 

          In World War II, the 231-Z Facility contained a total of 57 rooms including 20 laboratories, several process and chemical receiving and storage rooms, offices, change room facilities designed to accommodate 190 employees, air conditioning equipment, a distilled water system, ventilation and exhaust systems, and a compressed air system.  Six of the laboratories were known as "cell laboratories," and served as the major centers where the actual Pu isolation process was carried out.  All of the rooms except for one rest room were located on the first floor, with the second floor serving as a pipe and service loft containing duct work and filters for the ventilation and exhaust systems.

 

     The interior of the 231-Z Building was configured with two 8 foot (2.44‑meter) wide, north and south corridors, A and B; one on each side of the (6) cell laboratories with emergency exits to the outside of the building.  Corridors C and D ran east and west, connecting with corridor B.  Corridors E and F ran north and south separating laboratories and intersect corridors C and D.  Two concrete stairways led to the second floor, and below-grade piping led to a waste disposal system.  This piping was modified in 1948 to achieve additional control of 231-Z process wastes.

 

          The 231-Z Building foundations consisted of reinforced concrete piers with spread footings and concrete walls with spread footings.  Floors were reinforced concrete varying from 4‑inches (10.16‑centimeters) to 12‑inches (30.48 centimeters) in thickness.  The walls and ceilings of the cell laboratories and Vaults A and B were reinforced concrete 1 foot thick.  The roof was likewise reinforced concrete 4‑inches thick and was covered with built-up felt, gravel surface roofing containing numerous openings for intake and exhaust ducts.  The walls, floors, ceilings, and equipment in rooms 1 to 6, 8, 27, 31 to 45, Vaults A and B, and corridors A, B, C, D, E, and F were painted with "Amercoat" to obtain non-porous surfaces.[lxxxix]

 

 

4.1.10  The Bismuth-Phosphate Process

 

          The bismuth phosphate essentially dissolved the jackets off of irradiated U fuel elements, then dissolved the fuel itself, and then carried out a series of precipitations followed by centrifugation and re-dissolving of the precipitate cake.  The valent state of the Pu-239 (known as "product" at this stage) was manipulated so that it would stay with, or separate from, the various solutions and precipitate cakes produced in the operations.  In the +4 (tetravalent) state, the Pu-239 would carry with the bismuth phosphate-based solutions.  In the +6 valent state (hexavalent), the Pu-239 would not carry with the bismuth phosphate, and a by-product precipitation could be achieved.  The plutonium was reduced (taken to the tetravalent state) by adding oxalic acid or ferrous ions, and oxidized (taken to the hexavalent state) by adding sodium bismuthate (when bismuth phosphate was the carrier), or potassium permanganate (when lanthanum fluoride was the carrier).  Actually, lanthanum fluoride was known to be a better carrier of plutonium, in that it could carry with a smaller bulk or volume and could carry away the stronger lanthanides such as Cs, Sr and La.  However, it was/is very corrosive, and for that reason it was rejected for the main phase of the Hanford separations process.

 

 

4.1.11  Dissolving

 

          The first step in the separations process carried out at HEW was dissolving, a process that removed the aluminum fuel jackets from the uranium elements.  It was carried out in the dissolvers and metal solution storage tanks located in Sections 3 and 4 (Cells 5, 6 and 7) of the canyon buildings (T- and B-Plants).  The irradiated, jacketed fuel rods first were placed in boiling sodium hydroxide, to which sodium nitrate slowly was added (reduce the formation of hydrogen).  This step produced "coating removal waste."  Next, three metric tons of declad metal were charged into a dissolver.  Nitric acid was added in three increments, enough to dissolve one ton in each increment.  In order to keep the time cycle as short as possible, "a substantial metal heel" was lef[xc]t in the dissolver between charges.  New material was charged on top of this heel.

 

 

4.1.12  Extraction

 

          The second step in the process was the extraction step.  This operation separated the product (Pu-239) from most of the uranium.  It also removed about 90% of the fission products into what was called the metal waste solution.  The extraction step reduced the gamma radiation activity level by a factor of 10.  In the first extraction step, plutonium was kept in the +4 (reduced) valent state.  Bismuth nitrate and phosphoric acid were added to the solution that contained the dissolved fuel elements, causing the formation of bismuth phosphate.  A product precipitation (one that carried the Pu with it) then occurred.  The precipitate was centrifuged to separate the solid portion from the liquid.  The liquid portion was jetted away as waste.  The solid portion ("precipitate cake"), which contained the Pu, was placed in another tank and dissolved with nitric acid.  Sodium bismuthate or potassium permanganate were added to the plutonium-bearing solution to oxidize the Pu to the +6 state, and then sodium dichromate was added as a holding agent to keep the Pu steadily fixed in this state.  The BiPO4 then precipitated as a byproduct, leaving the Pu in solution.

 

 

4.1.13  Decontamination

 

     The third step, decontamination, essentially was a repetition of the  extraction process.  The final decontamination cycle reduced the gamma activity level by a factor of 10,000, giving an overall process "decontamination factor" of 100,000 below that of the original uranium solution.  The plutonium-bearing solution from the extraction step was reduced with the addition of ferrous ammonium sulfate.  Then, bismuth nitrate and phosphoric acid again were added, a product precipitation occurred, and the precipitate was centrifuged.  The solid portion, containing the Pu, was liquified with nitric acid, oxidized, and the remaining BiPO4 precipitated away as waste.[xci]

 

 

4.1.14  224 Bulk Reduction Process

 

          Plutonium-bearing solution was transferred from the "tail" ends of the canyon buildings to the 224 Buildings via underground piping.  The starting batch size in the latter facility was 330 gallons.  Here, the Pu solution from the 221 buildings was oxidized with sodium bismuthate.  Phosphoric acid then was added to produce a byproduct precipitation, leaving the Pu in solution.  Centrifuging then separated the solution and precipitate.  Nitric acid was added to dissolve the byproduct cake, and it became waste.  Next, the plutonium-bearing solution was oxidized with potassium permanganate (KMnO4).  Hydrogen fluoride and lanthanum salts were added, in what was known as the "crossover" step.  A lanthanum fluoride precipitate was produced, leaving hexavalent Pu in solution.

 

          Impurities were precipitated in a byproduct cake, as the fission products were carried with the lanthanum.  This byproduct cake contained all of the lanthanides (cerium, strontium, lanthanum, etc.) that the BiPO4 could not carry out of the stream.  The cake was dissolved in nitric acid, neutralized with sodium hydroxide, and sent to tanks for settling.  The plutonium solution then was reduced to +4 state by adding oxalic acid.  Lanthanum salts and hydrogen fluoride again were added, thus precipitating lanthanum fluoride that contained the Pu.  The precipitate was separated by centrifugation, and potassium hydroxide was added to metathesize the Pu lanthanum fluoride, forming a solid Pu lanthanum oxide.  (Metathesis is a chemical process to convert a solid to another solid.)  Any liquid was removed by centrifugation, and the solid Pu lanthanum oxide was then dissolved in nitric acid to form Pu nitrate.  By this time, the original 330-gallon batch that had entered the 224‑T Building had been concentrated to eight gallons (volume).[xcii]

 

 

4.1.15  231 Isolation Process

 

     Lastly, the plutonium nitrate from the 224 facilities was sent to the 231-Z Building for the final processing that could be done at the Hanford Engineer Works.  Hydrogen peroxide, sulfates, and ammonium nitrate were added to the plutonium-bearing solution.  The hexavalent Pu precipitated as plutonium peroxide.  Nitric acid then was added to dissolve this precipitate.  The Pu nitrate then was placed in small shipping cans and boiled right in these cans, using hot air.  It was reduced to a wet nitrate paste.  In this form, the Pu was stored in the 213-J and K vaults in the southeast end of Gable Mountain, and then shipped to the secret Los Alamos Site.  Each shipping can held about one kilogram (kg) of Pu.[xciii]

 

 

4.1.16  Earliest Operations

 

          Operating experiences during the initial months of canyon operations were described by DuPont as unusually satisfactory."[xciv]  No serious mechanical problems developed, except that the bowl of the centrifuge in Section 16 of T-Plant jammed against some dip tubes when it was run backwards on January 5, 1945.  The centrifuge was replaced via remote operations, partially decontaminated in a spare cell, and then buried in 1954 when it was determined that it could not be repaired.  This and other miscellaneous remote tasks gave operators confidence that "the Canyon Buildings can be operated remotely as planned and with somewhat less loss of fabricated equipment than originally anticipated."[xcv]

 

          During the next six months of canyon operations, procedures were standardized.  Technical efforts were directed towards reduced time cycles, as production sped for the special nuclear materials needed to win the war.  By mid-1945, emphasis had shifted to "a review of process technology and operating technique in an effort to improve efficiency and reduce waste losses."[xcvi]  Free nitric acid concentration was reduced to obtain an increase in the specific gravity of dissolver solutions.  The most significant improvement, however, came in the late summer, with the installation of piping to allow for intermediate solution transfer from storage to the precipitators in Section 6 (Cells 11 and 12).  This was a safety measure, as metal solution slightly in excess of charge requirements then could be taken from storage, agitated, and sampled so that the correct amount, based on critical mass limitations, could be transferred to the extraction sections of the plant.  Further safety improvements included more rigorous efforts to empty and decontaminate the precipitators used in the extraction and decontamination cycles.  These measures assured the prevention of Pu-239 buildup on equipment.

 

 

4.1.17  Early Process Changes

 

          The original HEW separations canyons were designed on the basis that one plant would have the capacity to process the output from one pile (reactor).  With each HEW reactor originally planned to produce one metric ton of metal (containing approximately 250 grams of product - Pu-239) per day, the earliest standard procedure for T-Plant involved starting a one metric-ton charge of metal into the dissolvers about every 26 hours.  However, by the summer of 1945, production tests had shown that charge size could safely be increased to 1.5 metric-tons of metal, "without noticeable effect of yield or equipment performance."[xcvii]  By September 1, process modifications enabled the plant to complete the processing of a charge in just 20 hours, with only a 10% allowance added onto the average process cycle for equipment repairs.

 

          Other very early changes included the elimination of potassium carbonate from the separations process in February 1945, and one month later, due to the unavailability of potassium hydroxide containing only 0.0005% iron impurity, the relaxation of process specifications for this chemical to allow for 0.005% iron impurity.  Overall, the first full-scale separations experiences at T-Plant and at the 224-T Bulk Reduction Building and the 231-Z Isolation Building, led to large reductions in many essential materials, per unit of production.  For example, the strength of the key dissolving agent nitric acid was decreased from an average of 95% to an average of 69% (a 33% reduction).  By September 1, 1945, other chemical requirements were reduced by an average of 41%, and potassium carbonate had been eliminated from the process altogether.

 

            Additional and ongoing process improvement studies carried out during the 1945-46 period were directed at:  simplification of operations to achieve reductions in process time, modification of the process to increase canyon capacity per batch, reduction in waste volumes, recovery of additional product from wastes, the establishment of better understandings of process safety and safety limits,

 

 



     a Zircaloy-2 is an alloy composed chiefly of zirconium, blended with small amounts of tin, iron, chromium and nickel.  It is not a trademark product name.

     aDetrex is a trademark of Detrex Chemical Industries.

     aDuponol-M-3 is a trademark of the E.I. du Pont de Nemours & Company.

     bAluminux and Diversey-415 were both trademark products of the Diversey Chemical Corporation.

     aIvory is a trademark of the Proctor and Gamble Co., Cincinnati, Ohio.

     bSutton is a trademark of the Sutton Engineering Corporation, Pittsburgh, PA.

     a Parker fittings were a trademark product of Parker Intangibles, Inc., of Wilmington, DE.

     b Neutron flux is a measure of the level of neutron excitation, movement or activity during the fission process.  Flux is measured in terms of the number of neutrons that strike one square centimeter in one second.

     a Amercoat is a trademark product of the Ameron Protective Coatings Division, Ameron, Inc., of Brea, California.



  [i].       DuPont, Construction, HAN-10970, Vol. IV, pp. 997-999.

  [ii].      DuPont, Construction, HAN-10970, Vol. IV, pp. 997-1001.

  [iii].     DuPont, Construction, HAN-10970, Vol, IV, p. 992.

  [iv].     DuPont, Construction, HAN-10970, Vol. IV, pp. 1021-1022.

  [v].      DuPont, Operation, HAN‑73214, Book 10, pp. 19‑26; and Simon, IN‑03400, p. 1.

  [vi].     Hanford Engineer Works, HW‑10475, Section A, pp. 1‑28; DuPont, Operation, HAN‑73214, Book 10, pp. 2-139; Weakley, HW‑58115‑DEL; Williams and Williamson, H‑3‑08393; Harlan and Williamson, H‑3‑8391; Kratzer, HW‑21450.

  [vii].    Harrington and Reuhle, eds., Uranium Production Technology, pp. 5‑12, 383‑425; and Greninger, HW-14110, pp. 72-73; and G.E. Hanford Co., HW-7504 pp. 49-50.

  [viii].    Weakley, HW‑58115‑DEL; U.S. DOE, DOE/RL‑90-11; AEC‑GE Study Group, GEH‑26434, p. 3.18; GE‑Bouillon and Griffith, HWS‑4955.

  [ix].     Drumheller, HW-47887; and Bell, HW‑68662, pp. 3‑8.

 [x].       DuPont, Operation, HAN‑73214, Book 10, pp. 24‑26.

 [xi].      National Lead of Ohio, "Uranium Feed Materials..." pp. 14‑15; Durum and Chamberlin, "300 Area Monthly Reports" (March 1946 and June 1946); Kidder, HW‑7-4049.

 [xii].      Bixler "300 Area Monthly Reports," 1947.

 [xiii].     Bixler, "300 Area Monthly Reports," December 1947 and January 1948, pp. 1‑2.

 [xiv].     Bixler, "300 Area Monthly Reports," December 1947, January 1948, April 1948; Bixler, Special Hazards Incident Investigations," Class I,  #85 and 86 (1948) and Class II, #9 (1948); Hervin, "Radiation Monitoring Coverage," July 1954; pp. 1‑2; U.S. DOE, DOE/RL‑90‑11, Appendix A.

 [xv].      Kent, HW‑25906, pp. 5‑6; Hochschild, HAN‑49157‑DEL; Corlett, HW‑38332, pp. 1‑6; Yost, HW‑39945, pp. 1‑4; Lane, HW‑47260, pp. 1‑4; Weakley, HW‑24494, pp. 1‑4; Weakley, HW‑27321, pp. 1‑2; Weakley, HW‑27734, pp. 2‑15, Brandt and Kraemer, HW‑28282, pp. 1‑4; Brandt, HW‑29871, pp. 1‑3; and p. 352; U.S. DOE, DOE/RL‑90‑11, p. A‑10; Harrington and Reuhle, eds., Uranium Production Technology, p. 352.

 [xvi].     Operation Managers, HW-59099, p. A-17; Operation Managers, HW-59463, pp. A‑16-17; Operation Managers, HW-59717, p. A-22; Operation Managers, HW‑60233-A, p. A-13; Operation Managers, HW-60505-A, p. A-18; Operation Managers, HW-63303, p. A-19

 [xvii].    Batch and Toyoda, HW-65722, pp. 3-6; Toyoda, HW-71389; Thorne, BNWL‑SA‑1770; Operation Managers, HW-63740-A, pp. A-16-17; Operation Managers, HW-64108, pp. A-15-16; Geering, HW-66267; Operation Managers, HW‑65459, p. A-18; Operation Managers, HW-65854, p. A-19; Operation Managers, HW-66237, p. A-14; Operation Managers, HW-67532, pp. A-16-17; Operation Managers, HW-67954, p. A-17.

 [xviii].   Clemans, WHC‑CM‑5‑20, Specification X-303.

 [xix].     Drumheller, HWS-6797; AEC/GE Study Group, GEH-26434, p. 3.36; U.S. DOE, DOE/RL‑90‑11; Clemans, WHC‑CM‑5‑20; Gill, HW‑69941.

 [xx].      U.S. DOE, DOE/RL-90-11, Section 3 and Appendix A.

 [xxi].     U.S. DOE, DOE/RL-90-11, Appendix A and pp. 3.1 through 3.9.

 [xxii].    Hanford Engineer Works, HW-10475-B; DuPont, Construction, HAN-10970, Vol. III, pp. 719‑735; Wahlen, WHC-EP-0273; IPD, "Maintenance Work Forecast, 1966;"  Russ, HW-30401, Vol. I.

 [xxiii].    Hanford Engineer Works, HW-10475-B, pp. 1,105-1,210; DuPont, Construction, HAN-10970, Vol. III, pp. 788-792, and 806-811; Russ, HW-30401, Vol. I.

 [xxiv].    Russ, HW-30401, Vol. 1.

 [xxv].    "Hanford Technical Manual," HW-10475-B; DuPont, Construction, Vol. III, pp. 788‑792; DuPont, Operation, Book 7, pp. 79-115; Jordan, HW‑3‑1121; Hanford Engineer Works, OUT-1462, pp. 13-14.

 [xxvi].    Jordan, HW-3-1121; Jordan and O'Connor, HW-3-1913; Janos, HW‑30083.

 [xxvii].   Menegus, HW-7-2744; Hanford Engineer Works, HW-10475-B; pp. 1110-1125; DuPont, Operation, HAN-73214, Book 7, pp. 107-114; Wende, HW-7-3486; Wende, HW-7-3834.

 [xxviii].  DuPont, Operation, HAN-73214, Book 15, pp. 138-141; Milton, HW-3-6898.

 [xxix].    U.S. AEC, AEC-1140 p. 7; Fry, HW-43749.

 [xxx].     Lewis, HW-07197; Haaga, HW-09603; Windsheimer, HW‑11374; Maider and MacCready, HW-10079.

 [xxxi].    Carbon and Fryar, HW-20425; Warekois and Reinker, HW-19281; Cole, HW-21659; Reinker and Bupp, HW-33842; Curtiss, HW‑55819.

 [xxxii].   DuPont, Operation, HAN-73214, Book 11, pp. 13-15; Handford Engineer Works, OUT-1462, pp. 64-69; DeNeal, DUN-6888.

 [xxxiii].  Wende, HW-13184.

 [xxxiv].  Reinker, HW-22110; Strand, HW-27778; Russ, HW‑30401, Vol. 1; IPD, HW-74094, Vol. 3; DeNeal, DUN-6888, p. 49.

 [xxxv].   Gast, HW-21761; Young, HW‑65760.

 [xxxvi].  Carbon and Fryar, HW-20425; Warekois and Reinker, HW-19281; Cole, HW-21659; Reinker and Bupp, HW-33842; Curtiss, HW‑55819.

 [xxxvii].  Windsheimer, HW-20841; Carbon and Fryar, HW-20425; Reinker, HW‑22110.

 [xxxviii]. Bupp, HW-29022; Reinker and Bupp, HW-33842.

 [xxxix].   Strand, HW-27778; Russ, HW-30401, Vol. I; Measley, HW-20379; Reinker and Bupp, HW-33842.

 [xl].      Jordan, HW-3-1121; Borgmier, HW‑21199.

 [xli].      Koop, HW-21789; Warren, HW-22423; DeMers, HW‑22687.

 [xlii].     Wells, HW-27318; Pitzer, HW-25656; Dalrymple, HW-26395; Lewis and Rohrbacher, HW‑29132; Strege, HW-32960.

 [xliii].    Alexander, HW-23153.

 [xliv].    Ritchey, HW-12492; Conley, HW-15943; Conley, HW-20342; Woods, HW-23163; Greninger, HW-25012.

 [xlv].     Miller, HW-29406; Etheridge, HW‑32664; Woods, HW-37698.

 [xlvi].    Fryar, HW-23361; Lewis and Rohrbacher, HW-29132; Wilson, HW‑31043-Rev; Lutton, HW-27158.

 [xlvii].   Wahlen, WHC-EP-0273, p. 20; DeNeal, DUN-6888, p. 9.

 [xlviii].   Paul and Stephens, HW-34467; Greager, HW-37033; Call and Rector, HW-30863; DeNeal, DUN‑6888, pp. 53-55.

 [xlix].    Amy, HW-24492; Lovington, HW-36224.

 [l].        Schilling and Hess, HW-25082; Lovington, HW-36224; Young, HW-43343;  McCarthy, HW-43456; Carlson and Trumble, HW-62471.

 [li].       Conley, HW-20342; Fox, HW-25345; Bupp, HW-28531; Pearl, HW-28739;  Bainard, HW-40694; Richman, HW-45070.  See also: Richman, HW-37694.

 [lii].      DuPont, Operation, HAN-73214, Book 11, pp. 76-77, 110; Hanford Eengineer Works, OUT-1492, p. 88; Kidder and Jordan, HW-3-2224.

 [liii].     Parker, HW-20959; Healy, HW-24578.  (Note:  For further discussion of the problems associated with radionuclides and Columbia River fish, see Gerber, On The Home Front, Chapter 5.)

 [liv].     Starkebaum, HW-33698; Conley, HW-24055; deHalas and Gay, HW-34821;  Hardin, HW-36021; Hardin, HW-38808; Hardin, HW-40703; Matsumoto, HW-43830; Koop, HW-50601.  (Note:  For further discussion of Hanford policy regarding operating purges, see Gerber, On the Home Front, Chapter 5.)

 [lv].      Trumble, HW-44708, Vols. 1 and 2; Russ, HW-30401, Vol. 1; Young, HW‑56230-RD; IPD, HW‑74094, Vol. 3; Stainken, HW-35589.

 [lvi].     Carbon and Gilbert, HW-37437.

 [lvii].     Greager, HW-37033; Talbott, HW-37304.

 [lviii].    Trumble, HW-44708, Vols. 1 and 2; Baker and McLenegan, HW‑43937;  Lyons, HW‑40363-Del.

 [lix].      Renn, HAN-65347; Dickeman, HW-65580; Trumble, HW-61580; DeNeal, DUN‑6888; Quinn, HAN-73578; Reid, HW-57497.  (Note: For a complete discussion of fuel fabrication changes and improvements at the Hanford Site, see Gerber, WHC‑MR-0388.)

 [lx].      Bainard, HW-49777; Heacock, HW-60596; Nilson, HW-63924.

 [lxi].      Deichman, HW-67741-Del; Dickeman, HW-65580; Bainard, HW-49777; Travis and Bloch, HAN-71403; Upson, HW-63562; CETO, HW‑61197 RD; Young, HW-65760; Young, HW-66468; Curtiss, HW‑55819.

 [lxii].     McLenegan, HW-62729; Corley, HW-61206; Watson, Fox, Harrison, Kempf, and Reinig, HW-65269; Trumble, HW-67131; Kratzer, HW‑67491; Curtiss, Fullmer, and Gilbert, HW-67491; Jones, HW‑62861; Robbins, HW-66363.

         

 [lxiii].    Trumble, HW-67131; Heacock and Jones, HW-SA-2287; IPD, "Acceptance of Completed Project...," November 8, 1961; Jessen, "Physical Completion Notice...," December 15, 1961.

 [lxiv].    IPD, "IPD Radiation Exposure Reduction Program," October 20, 1958; Walker, HW‑50351-Del; Faught, "Reevaluation of the Justification...," February 13, 1958; Porter, "Request for Mechanical Development...," November 17, 1958; DeNeal, DUN-6888.

 [lxv].     IPD, "Project Proposal...Project CG-786," December 2, 1957; Murray, "Construction Completion and Cost Closing Statement," February 13, 1959; G.E. Hanford Company, "Project Proposal, Revision 1...Project CG‑707," June 21, 1957; IPD, "Semi-Monthly Project Report," November 1958; IPD, "Project No. CGI-806...," June 15, 1961; Astley, "Pressure Monitor System Repair and Modification," March 28, 1962; Copeland, HW-63298;  Greninger, "Improvements to Gamma Monitor System...," June 27, 1960; Greninger, "Transmittal Letter...," September 6, 1961; IPD, "Acceptance of Completed Project," May 1, 1963; Corlett, "Fuel Rupture Monitor System," July 1, 1964; Astley, "Project CGI-904...," July 10, 1964; Simsen, IP64-15;  Hermann, HW-78840; Lyons, DUN-812; DUN, "Acceptance of Completed Project CGI-143 (105-B)," September 30, 1966; Lyons, RL-REA-676; Jessen, "Physical Completion Notice...," April 10, 1967.

 [lxvi].    "Hanford to Cut Back in 1965," January 8, 1964.

 [lxvii].   Hall and Jerman, HW-63653; Washington State Department of Health, CIC-161754; Spies, CIC-161740; Spies, CIC-161731; Dworsky, CIC-161744;  Silker, HW-56366; McCormack and Schwendiman, HW-61325; Foster and Junkins, HW-63654; Healy, HW‑60529; Geier, DUN-1906.  (Note:  A curie is a measure of radioactivity defined as the amount of radioactive material that has an activity of 3.7 X 1010 disintegrations per second.  About 14 curies of radioactivity were released to the atmosphere in the 1979 incident at Three Mile Island, Pennsylvania.  For a more complete discussion of the effects of radionuclides in the Columbia River, see Gerber, On the Home Front, Chapter 5.)

 [lxviii].   Herde, HW-3-5501; Coopey, HW-11662; Olson and Foster, HW-20055;  Schiffman, HW-72107; Parker, HW-32809.  (Note: This is a partial listing.  There are many similar studies.  For a complete discussion of the role of reactor effluent in the Columbia River, see Gerber, On the Home Front, chapter 5.)

 [lxix].    Foster, HW-49713; Foster, HW-54858; Junkins, HW-68096; Hall, HW-65733-RD; Hall and Jerman, HW-64517; Hall and Jerman, HW-63653.

 [lxx].     Silker, HW-56366.  See also:  HLO and IPD, HW‑70526.

 [lxxi].    Rieck, HW-72215; HLO and IPD, HW-70526; Ballowe, DUN-2231.

 [lxxii].    HLO and IPD, HW-70526; Geier and VanWormer, HW-75609; Geier, HW‑75949; Geier, HW-83775; Silker, BNWL‑CC‑1055; Geier, DUN-3935.[lxxii].22

 [lxxiii].   Honstead, HW-39465; Fuquay, HW-40371.

 [lxxiv].   Ballowe, DUN-2231.

 [lxxv].    Hanford Atomic Products Operation, HW-69000, Vol. I, p. 2.0-6; Stapp and Marceau, BHI-00627, Rev 0, p. 23.

 [lxxvi].   Hanford Atomic Products Operation, HW-69000, Vol. I, pp. 3.7-3-6; Coleman, DUN‑7342.

 [lxxvii].  Hanford Atomic Products Operation, HW-69000, Vol. I, pp. 3.6-2-8; Stapp and Marceau, BHI-0627, Rev. 0, Appendix C.

 [lxxviii]. Corbitt and Geier, DUN-5200-RD.

 [lxxix].   Erickson, UNI-1437, Rev. 2, pp. 5-6, 10, V-1; Scott, UNI-1960, pp. 1-3, 13-17; Newby and Marshall, UNI-2109; Lyon, UNI-2110; Nelson, UNI-3422; Nelson, UNI‑3329; Zaloudek and Ruff, UNI-3653 (PNL-5924); Zaloudek and Ruff, UNI-38994 (PNL-5930); Lee, UNI-4193; Nelson, UNI-4191 Rev. 1; Alzheimer and Gonzalez, UNI‑4285; Martek, UNI-4263; Lyon, UNI-1986; Cummings, UNI-2063; Rainey, UNI‑2182; Conn, UNI-2227 Rev. 1; DeMaria, UNI-3481 Rev 1; Shoemaker and Fuller, UNI-21016; Reeves, UNI-610 Rev. 1; Lechelt, UNI-2925; Lattin, UNI-3333; Rasmussen, UNI-3583; Stauch, UNI‑4210; Linschooten, UNI-4148; Pope, UNI-4239; Smith, UNI-4253; Sullivan, UNI-4225.

 [lxxx].    Hanford Engineer Works, HW‑10475‑B, pp. 910-919.  (Note:  The exact fuel storage times used in World War II are not known.  Following the war, storage times lengthened in order to allow for additional decay (stabilization) of radioisotopes such as Iodine 131.)

 [lxxxi].   Foskett, HW-18208; Stark, HW-22824.

[lxxxii]. Watson, Brendel and Shields, WHC0EP-0477.

 [lxxxiii].  Harrison, DUN-7711.

 [lxxxiv].  Nelson, UNI-2046.

 [lxxxv].  DuPont, IN-6263.

 [lxxxvi].  DuPont, Construction, HAN-10970, Vol. III, pp. 861-919.

 [lxxxvii]. DuPont, Construction, HAN-10970, Vol. III, pp. 905-908; Gerber, WHC‑MR‑0452.

 [lxxxviii].          DuPont, Construction, HAN-10970, Vol. III, pp. 913-915; Gerber, WHC‑MR‑0452.

 [lxxxix].  DuPont, Construction, HAN-10970, Vol. III, pp. 917-919; Gerber, WHC‑MR‑0452.

[xc]

 [xci].     Hanford Engineer Works, HW-10475-C; Stoller and Richards, Reactor Handbook, 2nd ed. pp. 227-234.

 [xcii].     Hanford Engineer Works, HW-10475-C.

 [xciii].    Hanford Engineer Works, HW-10475, Section C; Swartout, HW-3-2801.

 [xciv].    DuPont, Operation, HAN-73214, Book 12, p. 75.

 [xcv].     DuPont, Operation, HAN-73214, Book 12, p. 76; G.E. Hanford Co., "Property Disposal Report," #54-217, May 23, 1954.

 [xcvi].    DuPont, Operation, HAN-73214, Book 12, p. 145.

 [xcvii].   DuPont, Operation, HAN-73214, Book 12, p. 49.